AI data centers · 96 tracked from above

The buildings AI lives in.

Every large AI data center Epoch AI can see: who owns it, where it is, how much power it draws, what it cost, which chips are inside and when it switches on. Built from satellite images, permits and filings, and read fresh every few hours.

  • 96AI data centers tracked, 20 still being built
  • 15.1 GWof power for computing, drawn now
  • 38.2 GWplanned by the end of 2028, if the projects finish
All 96, as a skyline

Lit floors are running. Cranes are still building.

Each building is one AI data center, left to right in the order they first drew power. The tallest are the ones planned to draw the most. Tap one to open its page; on a phone, swipe sideways to see them all.

Skyline of 96 AI data centers, in the order they first drew power. Height is the power planned at each; lit windows show the power drawn now.
  • Lit windows: power drawn now
  • Dark windows: power still to come
  • Crane: still being built or growing
  • Taller: more power planned
15.1 GWdrawn for computing now, across 76 sites running
19.5 GWin all once cooling and the rest of each building are counted
15.8 millionchips' worth of computing, counted as Nvidia H100s
2.5×as much power by the end of 2028 if every project finishes
Every AI data center

Search all 96, sort any way.

Owner means who owns the chips inside, which isn't always who owns the building. Power is for the computing equipment, as Epoch AI estimates it. Each row opens the full record.

  1. Anthropic-Amazon New CarlisleNew Carlisle, IndianaAmazonUsed by Anthropic1.04 GW1.93 GW by Mar 2028$39bn
  2. Colossus 2Memphis, TennesseeSpaceXAIUsed by Anthropic, Cursor, SpaceXAI, Reflection946 MW1.53 GW by Feb 2027$36bn
  3. OpenAI Stargate AbileneAbilene, TexasOracleUsed by OpenAI824 MWRunning$31bn
  4. Microsoft Fairwater AtlantaFayetteville, GeorgiaMicrosoftUsed by OpenAI, Microsoft636 MWRunning$24bn
  5. DayOne NusajayaJohor Bahru, Johor, MalaysiaOwner not named473 MWRunning$18bn
  6. Meta PrometheusNew Albany, OhioMetaUsed by Meta471 MW1.02 GW by Jul 2028$18bn
  7. DayOne KempasJohor Bahru, Johor, MalaysiaOwner not named422 MWRunning$16bn
  8. Microsoft Fairwater WisconsinMount Pleasant, WisconsinMicrosoftUsed by OpenAI, Microsoft369 MW2.26 GW by May 2028$14bn
  9. Google Pryor (North)Pryor, OklahomaGoogleUsed by Google DeepMind368 MWRunning$14bn
  10. Colossus 1Memphis, TennesseeSpaceXAIUsed by Anthropic340 MWRunning$13bn
  11. Google New AlbanyNew Albany, OhioGoogleUsed by Google DeepMind333 MWRunning$13bn
  12. Google ColumbusColumbus, OhioGoogleUsed by Google DeepMind303 MW386 MW by Jul 2027$11bn
  13. Amazon Madison Mega SiteCanton, MississippiAmazonUsed by Anthropic284 MW683 MW by Mar 2028$11bn
  14. CoreWeave Denton TXDenton, TexasCoreWeaveUsed by OpenAI262 MW282 MW by May 2027$9.9bn
  15. Bridge Data Centres MY06Sedenak Tech Park, Johor, MalaysiaByteDance (likely)Used by ByteDance243 MWRunning$9.2bn
  16. Google BristowBristow, VirginiaGoogleUsed by Google DeepMind238 MWRunning$9.0bn
  17. QTS Richmond 1Sandston, VirginiaOwner not named238 MWRunning$9.0bn
  18. Google OmahaOmaha, NebraskaGoogleUsed by Google DeepMind237 MW395 MW by Jul 2028$9.0bn
  19. Google Council Bluffs (East)Council Bluffs, IowaGoogleUsed by Google DeepMind237 MWRunning$9.0bn
  20. Google PapillionPapillion, NebraskaGoogleUsed by Google DeepMind237 MWRunning$9.0bn
Where they are

Mostly American, for now.

77 of the 96 sites are in the US, planned to draw 33.1 GW between them. Epoch AI includes sites outside the US at a lower size threshold than US ones.

How fast it's growing

15.1 GW now. 38.5 GW planned.

Power for computing at every site Epoch AI tracks, month by month, by who owns the chips. After today it's Epoch's projection from what's under construction, so it can slip.

  • Google
  • Meta
  • Amazon
  • Microsoft
  • Oracle
  • SpaceXAI
  • Everyone else
  • Projected by Epoch AI
010 GW20 GW30 GW40 GW2021202220232024202520262027202820292030TodayProjected
The numbers, year by year
End ofGoogleMetaAmazonMicrosoftOracleSpaceXAIEveryone elseAll
20210 MW0 MW0 MW48 MW0 MW0 MW0 MW48 MW
20220 MW0 MW0 MW48 MW0 MW0 MW19 MW67 MW
2023160 MW45 MW0 MW135 MW0 MW0 MW61 MW401 MW
2024972 MW180 MW113 MW201 MW0 MW139 MW410 MW2.0 GW
20252.0 GW541 MW1.1 GW807 MW239 MW596 MW1.5 GW6.8 GW
2026*3.5 GW3.2 GW1.9 GW1.5 GW896 MW1.3 GW4.8 GW17.1 GW
2027*5.4 GW4.6 GW2.1 GW2.6 GW1.3 GW1.9 GW7.2 GW25.0 GW
2028*5.9 GW6.7 GW4.0 GW4.1 GW5.9 GW1.9 GW9.7 GW38.2 GW
2029*5.9 GW6.7 GW4.0 GW4.1 GW5.9 GW1.9 GW9.8 GW38.3 GW
Jan 2030*5.9 GW6.7 GW4.0 GW4.1 GW5.9 GW1.9 GW10.0 GW38.5 GW

IT power. * Epoch AI's projection.

What's inside

11.1M chips, give or take.

The AI chips Epoch AI counts at these sites today, by who designed them. Most counts are Epoch's estimates from each building's power; a few are what the companies disclosed.

Nvidia4.62 million chips9.52 million H100s' worth

B300 2.0M · B200 1.4M · H100 720K · H20 297K · H200 95K

Google4.19 million chips2.97 million H100s' worth

TPU v5e 1.8M · TPU v6e 1.4M · TPU v7 482K · TPU v5p 388K · TPU v4 150K

Amazon1.79 million chips1.18 million H100s' worth

Trainium2 1.8M

Huawei458,000 chips292,000 H100s' worth

Ascend 910C 289K · Ascend 950PR 128K · Ascend 910B 41K

= 100,000 chips. Nvidia's count includes chips bought by Amazon, Microsoft, Meta, Oracle and others; Google's and Amazon's are their own designs. H100s' worth compares computing power, so one newer chip can count as several.

The arguments

Power, water, bills and neighbors.

AI data centers are fought over in town halls and state capitals. Here is what each side says, and what has been measured, with who said it. We don't take a side.

Will they raise my electricity bill?

Power lines and plants built for data centers are paid for by someone. Who, and how much, is argued over by researchers, utilities and regulators.

$573 billionis Epoch AI's estimate of what the sites it tracks have cost to build so far, rising to $1.46 trillion if all are finished, with about $14 billion a year to run them.
  • Says

    A Harvard energy law expert says the cost of new grid equipment is shared by everyone on the grid.Everyone pays those costs Ari Peskoe, Harvard

    NPR, Oct 1, 2026

  • Estimate

    A 2024 Maryland estimate put the extra cost for households at about $168 to $216 a year, “primarily due to the data center boom”.

    NPR, Oct 1, 2026

  • Measured

    An analysis of US Energy Information Administration data found that states with the most growth in demand, data centers included, generally saw home electricity prices fall from 2019 to 2024.

    E&E News, Mar 19, 2026

  • Industry-funded study

    A study for the utilities' trade group, the Edison Electric Institute, found one region where data centers had pushed rates up.PJM is the only area where rates have increased because of data centers.

    E&E News, Mar 19, 2026

  • Government

    The White House asked the largest AI companies to “build, bring, or buy all of the energy needed for building and operating data centers, paying the full cost of their energy and infrastructure, no matter what.”

    The White House, Ratepayer Protection Pledge, Mar 4, 2026

How much electricity do they use?

All data centers, not only AI ones, as measured and forecast by the International Energy Agency and the US Department of Energy.

19.5 GWthe total drawn by the 76 running AI data centers Epoch AI tracks, cooling included, rising to about 50.4 GW if every project finishes.
  • Measured

    Data centers used about 1.5% of the world's electricity in 2024.Data centres accounted for around 1.5% of the world's electricity consumption in 2024, or 415 terawatt-hours (TWh).

    IEA, Energy and AI, 2025

  • Estimate

    The IEA expects that to more than double by 2030.Data centre electricity consumption is set to more than double to around 945 TWh by 2030.

    IEA, Energy and AI, 2025

  • Measured

    In the US, data centers used 176 TWh in 2023, about 4.4% of all electricity, up from 58 TWh in 2014.

    US Department of Energy, on Berkeley Lab's report, Dec 20, 2024

  • Estimate

    Berkeley Lab's scenarios put US data centers at “approximately 6.7 to 12% of total U.S. electricity by 2028”.

    US Department of Energy, Dec 20, 2024

How much water do they use?

Many data centers are cooled with water that evaporates. Others are cooled by air, which uses far less water but more power. Companies rarely publish site figures.

9 siteshave a water estimate from Epoch AI. The highest is Anthropic-Amazon New Carlisle at 21 million gallons a day; several air-cooled sites use almost none.
  • Measured

    US data centers directly used 17.4 billion gallons of water in 2023, according to Berkeley Lab's 2024 report.Data centers in the U.S. directly consumed 17.4 billion gallons of water in 2023

    MOST Policy Initiative, citing Berkeley Lab, Apr 8, 2026

  • Says

    In Cape Town, campaign groups say two proposed data centers (174 MW) would use over 4.4 billion litres a year, and have gone to court.

    Rest of World, Sep 17, 2026

Who is pushing back?

Towns, counties and states have paused or limited new data centers over power, water, noise and tax breaks. Others compete to win them for jobs and taxes.

  • Measured

    The National League of Cities found that 76 cities, counties or towns had at least attempted a pause on new data centers, and three had passed permanent bans. It says its list “is by no means exhaustive”.

    Route Fifty, on the National League of Cities' tracker, Aug 28, 2026

  • Measured

    In California, Food & Water Watch counts at least 26 resolutions, pauses or bans passed or proposed since June, including pauses in Oakland and San Francisco.

    CalMatters, Oct 22, 2026

  • Says

    An industry group argues data centers are core infrastructure, and that blanket bans mean towns “lose all your negotiating power”. Doug Kelly, American Edge Project

    CalMatters, Oct 22, 2026

  • Says

    A Cato Institute scholar says “Decisions around data centers are best handled by local communities”. Jennifer Huddleston, Cato Institute

    Route Fifty, Aug 28, 2026

More local fights, from Memphis to Cape Town, on Chips, data centers and power.

How we know

Counted from space, permits and filings.

Everything on these pages about each site comes from Epoch AI's AI data centers database, an independent research group's record of the largest AI data centers and how they were built. It is free to reuse with credit (CC BY 4.0). We read it straight from Epoch's download every few hours; this page was last built from data read on Nov 25, 2026.

Satellite images show when land clearing starts and how much cooling equipment, backup generators and substations go in; air permits (needed for backup diesel generators) confirm the details. Epoch counts total power as IT power times a peak PUE (power use effectiveness) of 1.2 for hyperscalers such as Google and Amazon and 1.4 otherwise. Capital cost comes from a cost-per-watt model: about $38 billion per gigawatt of IT power, covering chips, buildings, land and construction.

Epoch estimates its list covers about 44% of the world's AI computing power (it gives a range of 30% to 77%). So totals here are for the sites tracked, not the whole world.

Our rules

  • Running drawing power now, with no further growth in Epoch AI's projection.
  • Running and growing drawing power now, and Epoch AI projects more to come.
  • Being built under construction, not yet drawing power for computing.
  • “Now” is Epoch's latest estimate on or before the day the data was read; anything dated later is Epoch's projection and is labelled as one.
  • Users and owners carry Epoch's confidence: no label means confident, otherwise “likely” or “possibly”.

What to keep in mind

  • Epoch puts the cooling model's error at up to twice or half the real figure.
  • Plans change, and some sites have no permits Epoch can find.
  • Who uses a site is often secret, so users carry Epoch's confidence: confident, likely or possibly.
  • Smaller sites (under 100 MW) and obscure ones can be missed, and the list is mostly sites that came online in 2024 or later.

Method: Epoch AI's methodology · documentation. Spot a mistake? Tell us.