Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
No changes to the site since December 2025.
238 MW for computing333 MW in all5 buildings runningNo changes to the site since November 2025.
238 MW for computing333 MW in all5 buildings runningBuilding 5 is operational, based on a complete building and full carpark in a Google Earth image. Construction equipment around Building 1 and 2 has cleared up again.
238 MW for computing (was 190 MW)333 MW in all5 buildings runningBuilding 4 is operational, based on a complete building and full carpark in a Google Earth image. Building 5 does not seem quite operational given the empty carpark and construction activity at the perimeter.
190 MW for computing (was 142 MW)266 MW in all4 buildings runningBuilding 3 is operational, based on the building looking complete and the carpark to the south being full. Three more backup generators added to the Building 1 and 2 area, with a lot more construction equipment again (but this could be a laydown area for Richmond 2). Building 4 has cooling and backup generators fully installed. Building 5 has cooling installed, and backup generators partly installed.
142 MW for computing (was 94 MW)199 MW in all3 buildings runningBuilding 2 (retrofitted) is operational. This is based on Building 2 looking compelte, and construction around Building 1 and 2 being mostly cleared. A colored motion artifact on one of the Building 1 cooling tower fans suggests it is moving. Building 3 cooling is installed, backup generators partly installed. Building 4 shell is under construction.
94 MW for computing (was 47 MW)132 MW in all2 buildings runningBuilding 1 (retrofitted) is operational. This is based on it looking complete, and cooling towers possibly showing water vapor plumes, in this Google Earth image. Building 2 has chillers added to the roof and perimeter, and backup generators added to the perimeter. Cooling towers near Building 2 have been removed. Building 3 shell is under construction.
47 MW for computing66 MW in all1 building runningBuilding 1 and 2 retrofitting has begun (see Google Earth). Building 1 has chillers added to the roof and perimeter, and backup generators added to the perimeter.
No power for computing yetLand clearing begins for site expansion, some materials down at substation site. We assume that Buildings 1 and 2 are not running AI workloads at this point due to the lack of cooling infrastructure.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Feb 13, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Dominion Energy
Sandston, Virginia
Address in Epoch AI's records: 6000 Technology Blvd, Sandston, VA 23150.
Also in Virginia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Richmond 1 factsheetqtsdatacenters.com
- Environmental permit detailing power generationdeq.virginia.gov
- QTS Richmond 1 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets