Running and growing · New Carlisle, Indiana

Anthropic-Amazon New Carlisle

Anthropic-Amazon New Carlisle is an AI data center in New Carlisle, Indiana, owned by Amazon and used by Anthropic. Epoch AI estimates it draws 1.04 GW for computing, rising to 1.93 GW by Mar 2028.

  • 1.04 GWfor computing now, the most of the 96 Epoch AI tracks
  • 1.93 GWplanned by Mar 2028
  • $39 billionbuilt so far, Epoch AI's estimate in 2025 dollars
1.04 GW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW500 MW1 GW1.5 GW2 GW2.5 GW2025202620272028Feb 9, 2024: 0 MWJun 23, 2025: 398 MWDec 23, 2025: 626 MWMar 23, 2026: 910 MWOct 19, 2026: 1.04 GWMar 17, 2028: 1.93 GW (projected)0 MW500 MW1 GW1.5 GW2 GW2.5 GW2025202620272028Feb 9, 2024: 0 MWJun 23, 2025: 398 MWDec 23, 2025: 626 MWMar 23, 2026: 910 MWOct 19, 2026: 1.04 GWMar 17, 2028: 1.93 GW (projected)
  1. Epoch AI's projection

    Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an air quality permit filed in May 2026, and the compute capacity is based on Trainium3 chips.

    1.93 GW for computing (was 1.04 GW)2.31 GW in all32 buildings running
  2. Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.

    1.04 GW for computing (was 910 MW)1.24 GW in all18 buildings running
  3. Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.

    910 MW for computing1.09 GW in all16 buildings running
  4. Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.

    910 MW for computing (was 626 MW)1.09 GW in all16 buildings running
  5. Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.

    626 MW for computing751 MW in all11 buildings running
  6. Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.

    626 MW for computing (was 398 MW)751 MW in all11 buildings running
  7. Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".

    398 MW for computing478 MW in all7 buildings running
  8. Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.

    398 MW for computing478 MW in all7 buildings running
  9. Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.

    398 MW for computing478 MW in all7 buildings running
  10. Roof complete on building 11

    No power for computing yet
  11. Land clearing begins in the southern section

    No power for computing yet
  12. Land clearing begins in the northern section

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Oct 19, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

1.04 GWIT power, for the computersOct 19, 2026
1.24 GWtotal power, cooling included
1.93 GWIT power planned by Mar 2028
818,000computing power, counted as Nvidia H100 chips
$39 billioncapital cost so far: $27 billion for chips and computers, $12 billion for the buildings, power and land
$73 billioncapital cost once finished, by Mar 2028
$0.9 billiona year to run (power, staff, upkeep, taxes, water)
21 million gallonsof water a day, Epoch AI's estimate (Oct 19, 2026)

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Amazon

Uses it

Anthropic

Part of

Project Rainier

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
Trainium2Amazon1,044,980 est.Oct 19, 2026All 18 buildings operational. Same model.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Air Construction Permit application for the northern portiondrive.google.com
  2. Backup diesel generator referenced in the permitcat.com
  3. Announcement of Project Rainier coming onlineaboutamazon.com
  4. Air permit for Buildings 19-32, suggesting expansion to 2.3 GW total facility powert.co
  5. Anthropic-Amazon New Carlisle in Epoch AI's directoryepoch.ai
  6. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/anthropic-amazon-new-carlisle