Intelligence Progress
AI data centers by US state

AI data centers in Mississippi.

Epoch AI tracks 2 of its 96 large AI data centers in Mississippi, drawing 512 MW for computing now and 1.52 GW once the projects there finish. Owners: Amazon.

  • 2AI data centers tracked
  • 512 MWfor computing now, #10 of 40 places
  • 1.52 GWplanned, if every project finishes
2 sites

Every one in Mississippi.

Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.

  1. Running and growingAmazon Madison Mega SiteCanton, Mississippi · Amazon284 MW now683 MW by Mar 2028
  2. Running and growingAmazon RidgelandRidgeland, Mississippi · Amazon228 MW now840 MW by Sep 2028
Power over time

512 MW now, 1.52 GW planned.

Power for computing at the sites in Mississippi, month by month. After today it is Epoch AI's projection.

  • Mississippi
  • Projected by Epoch AI
00.5 GW1 GW1.5 GW2 GW20262027202820292030TodayProjected
The numbers, year by year
End ofMississippiAll
2025284 MW284 MW
2026*512 MW512 MW
2027*568 MW568 MW
2028*1.5 GW1.5 GW
2029*1.5 GW1.5 GW
Jan 2030*1.5 GW1.5 GW

IT power. * Epoch AI's projection.

Who owns them

The companies here.

From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.