Start Campus Sines Data Campus is an AI data center in Sines, Portugal, owned by Nscale and used by Microsoft. Epoch AI estimates it draws 33 MW for computing, rising to 233 MW by Sep 2027.

  • 33 MWfor computing now, #72 of the 96 Epoch AI tracks
  • 233 MWplanned by Sep 2027
  • $1.3 billionbuilt so far, Epoch AI's estimate in 2025 dollars
33 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW250 MW300 MW20232024202520262027Jan 1, 2022: 0 MWApr 3, 2026: 33 MWSep 30, 2027: 233 MW (projected)0 MW50 MW100 MW150 MW200 MW250 MW300 MW20232024202520262027Jan 1, 2022: 0 MWApr 3, 2026: 33 MWSep 30, 2027: 233 MW (projected)
  1. Epoch AI's projection

    Building 2 (SIN02) projected to be operational. This is based on the timeline provided in the factsheet for the site. We expect VR200 GPUs to be used as a lot of those chips will have already been available in September 2027, and the "up to 600kW racks" in the factsheet suggest they are aiming for this.

    233 MW for computing (was 33 MW)280 MW in all2 buildings running
  2. Satellite imagery shows two black outlines, suggesting two buildings going up on a second adjacent site. There is an outline of another building as well. Further to the east, there is land clearing.

    33 MW for computing40 MW in all1 building running
  3. Building 1 (SIN01) operational for AI, with the first deployment of 12,600 Nvidia GB300 NVL72s to the site being reported completed "Q1 2026" based on the corporate announcement. Land clearing also begins for Building 2 (SIN02), with faint dirt outlines for roads and building foundations visible.

    33 MW for computing40 MW in all1 building running
  4. Building 1 (SIN01) is completed, but at this point it likely not being used for AI as the collaboration with Microsoft that resulted in GB300s did not occur until Q1 2026. The completion is based both on satellite imagery, which shows the building fully completed, and a March 2025 article that says it "has been in operation since October", which is October of 2024.

    No power for computing yet
  5. Land clearing begins for Building 1 (SIN01)

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Aug 16, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

33 MWIT power, for the computersAug 16, 2026
40 MWtotal power, cooling included
233 MWIT power planned by Sep 2027
32,000computing power, counted as Nvidia H100 chips
$1.3 billioncapital cost so far: $0.9 billion for chips and computers, $0.4 billion for the buildings, power and land
$8.8 billioncapital cost once finished, by Sep 2027
$0.0 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Nscale

Uses it

Microsoft

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
B300Nvidia12,600 disclosedApr 3, 2026First deployment set to go live by Q1 2026 according to announcement.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Website for the sitestartcampus.pt
  2. Factsheet for the full site23712035.hs-sites.com
  3. Article detailing Microsoft collaboration and GPU amountslp.startcampus.pt
  4. Start Campus Sines Data Campus in Epoch AI's directoryepoch.ai
  5. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/start-campus-sines-data-campus