Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.
133 MW for computing179 MW in all2 buildings runningBuildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.
133 MW for computing179 MW in all2 buildings runningWe believe Buildings 1 and 2 are still undergoing testing due to construction equipment and unfinished land surrounding the data center sites, as well as color motion artifacts on a small number of the cooling fans.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 2, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 59,906 est. | Dec 7, 2025 | B300 NVL72 assumed from commissioning timeline and estimates from https://epoch.ai/data/ai-chip-owners. Count = Total IT power / IT overhead / server power x 72. |
Eagle Mountain, Utah
Address in Epoch AI's records: 1275 N Community Cir, Eagle Mountain, UT 84005.
Also in Utah
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Expansion announcement by Metafacebook.com
- Report on Williams Company gas-fired plant under construction adjacent to data centeukozvhzgrcnkcatjqfoo.supabase.co
- Meta Eagle Mountain in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-eagle-mountain