AI data centers in Nevada.

Epoch AI tracks 1 of its 96 large AI data centers in Nevada, drawing 161 MW for computing now and 300 MW once the projects there finish. Owners: Google.

  • 1AI data center tracked
  • 161 MWfor computing now, #19 of 40 places
  • 300 MWplanned, if every project finishes
1 site

Every one in Nevada.

Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.

  1. Running and growingGoogle Storey CountyClark, Nevada · Google161 MW now300 MW by Jun 2027
Power over time

161 MW now, 300 MW planned.

Power for computing at the sites in Nevada, month by month. After today it is Epoch AI's projection.

  • Nevada
  • Projected by Epoch AI
00.25 GW0.5 GW2024202520262027202820292030TodayProjected
The numbers, year by year
End ofNevadaAll
202381 MW81 MW
202481 MW81 MW
2025161 MW161 MW
2026*161 MW161 MW
2027*300 MW300 MW
2028*300 MW300 MW
2029*300 MW300 MW
Jan 2030*300 MW300 MW

IT power. * Epoch AI's projection.

Who owns them

The companies here.

From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.