Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 4 shell mostly complete, Building 5 steel framing is underway.
237 MW for computing284 MW in all3 buildings runningLand cleared for Building 4 and 5.
237 MW for computing284 MW in all3 buildings runningBuilding 3 looks operational.
237 MW for computing (was 79 MW)284 MW in all3 buildings runningBuilding 2 assumed operational due to vapor from cooling towers. Building 3 5/7 cooling towers installed.
79 MW for computing95 MW in all1 building runningBuilding 1 assumed operational due to vapor from cooling towers. Building 2 4/7 cooling towers installed. Building 3 roof complete coverage but unfinished.
79 MW for computing95 MW in all1 building runningBuilding 2 under construction. Building 3 begins construction.
No power for computing yetLand clearing begins for Building 1 of expansion.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 4, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v5e | 261,166 est. | Aug 3, 2024 | Cumulative through Buildings 2-3 (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 70,453 est. | Aug 3, 2024 | Buildings 2-3 (Q2 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v4 | 115,242 est. | Jan 23, 2023 | Building 1 (Q1 FY23 mix for new capacity. The one-quarter purchase lag from the operational date points to Q4 FY22, which predates the TPU_Production table, so the earliest available quarter Q1 FY23 is used). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Papillion, Nebraska
Address in Epoch AI's records: 14651-15249 Gold Coast Rd 68138 Papillion Nebraska, USA.
Also in Nebraska
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Draft basis of air permit with details of cooling towersdrive.google.com
- 2025 Environmental Reportsustainability.google
- Google Papillion in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-papillion