Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per Kenanga via The Star; JDC4 phases Sep-25/Sep-26/Sep-27 per MIDF. The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park (Kenanga, 9 Dec 2024).
284 MW for computing (was 113 MW)389 MW in all5 buildings running Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.
113 MW for computing155 MW in all2 buildings runningBuilding 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).
113 MW for computing (was 100 MW)155 MW in all2 buildings runningBuilding 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this video. Solar panels are also being installed to the north west of the campus.
100 MW for computing (was 20 MW)138 MW in all2 buildings runningBuilding 1 is operational with Nvidia GB200s, according to the local investment development authority.
20 MW for computing26 MW in all1 building runningLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 13, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 51,192 est. | May 15, 2026 | Building 1 expansion |
| B200 | Nvidia | 9,576 est. | Nov 3, 2025 | Building 1 (JDC2) "fully fitted with the NVIDIA NVL72 Grace Blackwell (GB200) GPUs" at disclosed 20MW IT. https://www.midf.com.my/sites/corporate/files/2025-11/ytl_power-cu-all_systems_go_for_ai_dc-mbsbr-031125.pdf |
Kulai, Johor, Malaysia
Address in Epoch AI's records: YTL Green Data Centers, Kulai, Johor, Malaysia.
Also in Malaysia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Official YTL page for the campusytldatacenters.com
- YTL press release on the use of GB200'sytlpowerinternational.com
- Aerial footage including the campusyoutube.com
- YTL Johor in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/ytl-johor