Being built · Holly Ridge, Louisiana

Meta Hyperion

Meta Hyperion is an AI data center in Holly Ridge, Louisiana, owned by Meta and used by Meta. It is being built; Epoch AI projects 1.63 GW for computing by Jan 2028.

  • 1.63 GWplanned by Jan 2028
Being built
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW500 MW1 GW1.5 GW2 GW2025202620272028Dec 20, 2024: 0 MWJan 1, 2028: 1.63 GW (projected)0 MW500 MW1 GW1.5 GW2 GW2025202620272028Dec 20, 2024: 0 MWJan 1, 2028: 1.63 GW (projected)
  1. Epoch AI's projection

    First phase is operational, based on a Meta blog post. We assume that this aligns with the three natural gas turbines being completed, for a total of 2262 MW capacity, but that these turbines have a backup role. This is close to the 1800 MW of load requested from the grid. Meta claims that "The Hyperion cluster will have a 5-gigawatt capacity once complete", but so far there is no concrete evidence for this happening at the Holly Ridge site alone.

    1.63 GW for computing2.20 GW in all9 buildings running
  2. Epoch AI's projection

    New power stations are in service for a 1.8 GW load at Holly Ridge. However, the data center is still not operational.

    No power for computing yet
  3. Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.

    No power for computing yet
  4. Foundations are underway for the main buildings, and the overall layout aligns with the architectural renderings published in 2025.

    No power for computing yet
  5. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Apr 19, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

None yetIT power, for the computersApr 19, 2026
None yettotal power, cooling included
1.63 GWIT power planned by Jan 2028
None yetcomputing power, counted as Nvidia H100 chips
–capital cost so far
$62 billioncapital cost once finished, by Jan 2028
–a year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Meta

Uses it

Meta

Part of

Hyperion

Investors

Not named

Builders

Mortenson

Power from

Entergy

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Data center profile by Metadatacenters.atmeta.com
  2. Entergy's application for generation and transmission resourcesdrive.google.com
  3. MISO update with 1.8 GW substation plandrive.google.com
  4. S&P Global ratings research with 2.064 GW campus detailsspglobal.com
  5. Meta Hyperion in Epoch AI's directoryepoch.ai
  6. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-hyperion