Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 1 still operational. No new major developments since the April image, though the large land clearing to the southwest is now much more clearly visible. Bulk is saying this expansion could include AI datacenters, but we don't have any confirmation this expansion is for CoreWeave yet.
42 MW for computing55 MW in all1 building runningBuilding 1 perimeter is now fully paved. No other significant changes to Building 1 since the July 2025 image.
42 MW for computing55 MW in all1 building runningBuilding 1 appears to be operational based on satellite imagery, so we model it as operational from this date. In addition, Bulk said CoreWeave’s Norway AI deployment was expected to be operational by summer 2025. Since this lines up nicely with the new 42 MW building, we assume the 42 MW of Building 1 is fully leased by CoreWeave.
42 MW for computing55 MW in all1 building runningThis article from Bulk Infrastructure says construction had started on the "next 42 MW facility" by this date, so we model it as starting from here.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 15, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 20,096 est. | Jul 27, 2025 | CoreWeave and Bulk disclosed a GB200 NVL72 deployment at N01, expected operational by summer 2025. The unit count is estimated using the 42 MW DCM102 facility, Bulk's 50-100 kW/rack density disclosure, and NVIDIA's 72 Blackwell GPUs per GB200 NVL72 rack. |
Øvrebø, Norway
Address in Epoch AI's records: Stølevegen 39, 4715 Øvrebø, Norway.
Also in Norway
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- CoreWeave/Bulk N01 partnership announcementbulkinfrastructure.com
- Bulk N01 expansion announcementbulkinfrastructure.com
- Bulk N01 campus brochure with 5-data-center planbulkinfrastructure.com
- CoreWeave Norway in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-norway