Intelligence Progress
Running · Sandston, Virginia

QTS Richmond 2

QTS Richmond 2 is an AI data center in Sandston, Virginia. Epoch AI estimates it draws 180 MW for computing.

  • 180 MWfor computing now, #29 of the 96 Epoch AI tracks
  • $6.8 billionbuilt so far, Epoch AI's estimate in 2025 dollars
180 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW2023202420252026Apr 1, 2022: 0 MWFeb 4, 2025: 72 MWDec 31, 2025: 144 MWMay 14, 2026: 180 MW0 MW50 MW100 MW150 MW200 MW2023202420252026Apr 1, 2022: 0 MWFeb 4, 2025: 72 MWDec 31, 2025: 144 MWMay 14, 2026: 180 MW
  1. Building 5 is estimated to be operational, based on the previous entry.

    180 MW for computing (was 144 MW)252 MW in all5 buildings running
  2. Building 5 still has construction work at the perimeter, but given how close it looks to completion, we estimate it's only about 3 months away from operational.

    144 MW for computing202 MW in all4 buildings running
  3. Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construction work.

    144 MW for computing (was 72 MW)202 MW in all4 buildings running
  4. The west substation looks complete, based on a Google Earth image. This image also shows one corner of Building 5 that still has construction work, so it's probably not operational.

    72 MW for computing101 MW in all2 buildings running
  5. Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.

    72 MW for computing101 MW in all2 buildings running
  6. Still not many cars parked at Building 1 and 2, and the east substation looks very close to completion, based on a Google Earth image.

    No power for computing yet
  7. Building 1 and 2 look complete but we don't think they are operational, as the substation is still under construction.

    No power for computing yet
  8. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of May 14, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

180 MWIT power, for the computersMay 14, 2026
252 MWtotal power, cooling included
180 MWthe most Epoch AI projects here
183,000computing power, counted as Nvidia H100 chips
$6.8 billioncapital cost so far: $4.7 billion for chips and computers, $2.1 billion for the buildings, power and land
$6.8 billioncapital cost, finished
$0.2 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Not named by Epoch AI

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Dominion Energy

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Richmond 2 factsheetqtsdatacenters.com
  2. Environmental permit detailing power generationdeq.virginia.gov
  3. QTS Richmond 2 in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/qts-richmond-2