Running · Council Bluffs, Iowa

Google Council Bluffs (East)

Google Council Bluffs (East) is an AI data center in Council Bluffs, Iowa, owned by Google and used by Google DeepMind (possibly). Epoch AI estimates it draws 237 MW for computing.

  • 237 MWfor computing now, #18 of the 96 Epoch AI tracks
  • $9.0 billionbuilt so far, Epoch AI's estimate in 2025 dollars
237 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW250 MW300 MW2023202420252026Sep 6, 2022: 0 MWNov 19, 2024: 79 MWJun 15, 2025: 158 MWJul 7, 2026: 237 MW0 MW50 MW100 MW150 MW200 MW250 MW300 MW2023202420252026Sep 6, 2022: 0 MWNov 19, 2024: 79 MWJun 15, 2025: 158 MWJul 7, 2026: 237 MW
  1. Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the southwest seems to be setting up for two more buildings.

    237 MW for computing (was 158 MW)284 MW in all3 buildings running
  2. Building 3 has all 34 backup generators installed and 4 cooling towers installed, with 3 more cooling towers under construction. There are gaps between cooling towers suggesting that more could be added. Buildings 1 and 2 are running close to full capacity, given that water vapor is coming out of 5 of 7 cooling towers for each building. The land cleared in the southwest appears to be shaped for two more similar buildings, with notches for substations.

    158 MW for computing190 MW in all2 buildings running
  3. Land clearing begins in the southwest, suggesting more buildings are planned.

    158 MW for computing190 MW in all2 buildings running
  4. Building 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.

    158 MW for computing (was 79 MW)190 MW in all2 buildings running
  5. Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there were almost no cars parked. By February 2025, Google Earth shows no construction work and many cars. So our best guess is in the middle, in November 2024. Building 3 roof is complete.

    79 MW for computing95 MW in all1 building running
  6. Land clearing begins for east buildings

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Jul 7, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

237 MWIT power, for the computersJul 7, 2026
284 MWtotal power, cooling included
237 MWthe most Epoch AI projects here
256,000computing power, counted as Nvidia H100 chips
$9.0 billioncapital cost so far: $6.2 billion for chips and computers, $2.8 billion for the buildings, power and land
$9.0 billioncapital cost, finished
$0.2 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Google DeepMind (possibly)

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
TPU v6eGoogle125,181 est.Jul 7, 2026Cumulative (Q2 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
TPU v7Google41,923 est.Jul 7, 2026Cumulative (Q2 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
TPU v5pGoogle54,261 est.Jun 15, 2025Cumulative (Q2 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
TPU v5eGoogle84,203 est.Nov 19, 2024First operational capacity (Q4 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Construction permit application form with site addressprograms.iowadnr.gov
  2. Construction permit application form with backup generator dataprograms.iowadnr.gov
  3. Google Council Bluffs (East) in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-council-bluffs-east