Running and growing · Berwick, Pennsylvania

AWS Berwick

AWS Berwick is an AI data center in Berwick, Pennsylvania, owned by Amazon and used by Anthropic (possibly). Epoch AI estimates it draws 108 MW for computing, rising to 169 MW by Aug 2027.

  • 108 MWfor computing now, #51 of the 96 Epoch AI tracks
  • 169 MWplanned by Aug 2027
  • $4.1 billionbuilt so far, Epoch AI's estimate in 2025 dollars
108 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW202220232024202520262027Jul 1, 2021: 0 MWSep 9, 2025: 47 MWJan 7, 2026: 77 MWAug 1, 2026: 108 MWAug 1, 2027: 169 MW (projected)0 MW50 MW100 MW150 MW200 MW202220232024202520262027Jul 1, 2021: 0 MWSep 9, 2025: 47 MWJan 7, 2026: 77 MWAug 1, 2026: 108 MWAug 1, 2027: 169 MW (projected)
  1. Epoch AI's projection

    Building 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size.

    169 MW for computing (was 108 MW)212 MW in all4 buildings running
  2. Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.

    108 MW for computing (was 77 MW)139 MW in all3 buildings running
  3. Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.

    77 MW for computing102 MW in all2 buildings running
  4. The SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.

    77 MW for computing102 MW in all2 buildings running
  5. Building 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date.

    77 MW for computing (was 47 MW)102 MW in all2 buildings running
  6. Building 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.

    47 MW for computing66 MW in all1 building running
  7. Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule.

    No power for computing yet
  8. AWS acquires the Cumulus/Talen building campus for $650M.

    No power for computing yet
  9. Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.

    No power for computing yet
  10. Land clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Aug 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

108 MWIT power, for the computersAug 1, 2026
139 MWtotal power, cooling included
169 MWIT power planned by Aug 2027
81,000computing power, counted as Nvidia H100 chips
$4.1 billioncapital cost so far: $2.8 billion for chips and computers, $1.3 billion for the buildings, power and land
$6.4 billioncapital cost once finished, by Aug 2027
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
129,000 gallonsof water a day, Epoch AI's estimate (Aug 1, 2026)

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Amazon

Uses it

Anthropic (possibly)

Part of

Project Rainier (possibly)

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
Trainium2Amazon123,838 est.Aug 1, 2026Building 3 is added to the operational estimate. Quantity is calculated from the modeled three-building IT power using the Trainium2 chips-per-IT-MW assumption.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. NYT reporting that one of the Project Rainier sites may be in Pennsylvanianytimes.com
  2. Talen SEC filing detailing the $650M sale of the Cumulus data center campus to AWSsec.gov
  3. Pennsylvania PUC filing describing the planned 16-building AWS data center developmentpuc.pa.gov
  4. SRBC filing covering AWS campus expansion and water-use planssrbc.gov
  5. AWS Berwick in Epoch AI's directoryepoch.ai
  6. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/aws-berwick