Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size.
169 MW for computing (was 108 MW)212 MW in all4 buildings running Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.
108 MW for computing (was 77 MW)139 MW in all3 buildings runningBuildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.
77 MW for computing102 MW in all2 buildings runningThe SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.
77 MW for computing102 MW in all2 buildings runningBuilding 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date.
77 MW for computing (was 47 MW)102 MW in all2 buildings runningBuilding 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.
47 MW for computing66 MW in all1 building runningBuilding 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule.
No power for computing yetAWS acquires the Cumulus/Talen building campus for $650M.
No power for computing yetCumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.
No power for computing yetLand clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| Trainium2 | Amazon | 123,838 est. | Aug 1, 2026 | Building 3 is added to the operational estimate. Quantity is calculated from the modeled three-building IT power using the Trainium2 chips-per-IT-MW assumption. |
Berwick, Pennsylvania
Address in Epoch AI's records: 1125 Electron Ave, Berwick, PA 18603.
Also in Pennsylvania
More of Amazon's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- NYT reporting that one of the Project Rainier sites may be in Pennsylvanianytimes.com
- Talen SEC filing detailing the $650M sale of the Cumulus data center campus to AWSsec.gov
- Pennsylvania PUC filing describing the planned 16-building AWS data center developmentpuc.pa.gov
- SRBC filing covering AWS campus expansion and water-use planssrbc.gov
- AWS Berwick in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/aws-berwick