Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the Socrates the Younger power plant. The power plant is operational by Q3 of 2028 based on the project schedule. It is announced to produce a maximum of 250MW.
1.02 GW for computing (was 868 MW)1.33 GW in all27 buildings running - Epoch AI's projection
Building 15 (Vantage) operational, based on it starting construction about 3 months after Building 14.
868 MW for computing (was 804 MW)1.13 GW in all21 buildings running - Epoch AI's projection
Building 14 (Vantage) is operational, based on it starting construction about 3 months after Building 13.
804 MW for computing (was 740 MW)1.04 GW in all20 buildings running - Epoch AI's projection
Building 13 (Vantage) is operational, based on the pace of construction seen in earlier images.
740 MW for computing (was 676 MW)962 MW in all19 buildings running - Epoch AI's projection
Socrates South and Socrates North gas power plants are fully operational, enabling the operability of Buildings 11-12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and Socrates North. This is based on documents stating "late Third or early Fourth Quarter of 2026", "late 2026", "November 2026", "third quarter of 2026". The timeline also lines up with RAAD drone imagery from 09/08/26 seeing operating turbines at Socrates South and a full set of turbines installed but not yet operating at Socrates North.
676 MW for computing (was 471 MW)878 MW in all18 buildings running Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.
471 MW for computing (was 368 MW)612 MW in all10 buildings runningBuilding 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed except for 21 and 27.
368 MW for computing478 MW in all6 buildings runningThe Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of tent buildings has begun east of Buildings 16-20.
368 MW for computing478 MW in all6 buildings runningBuildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their right side which are not fully installed. Building 14 has chillers installed. Buildings 16-20 roofs are complete. The Socrates South power plant to the right of Buildings 7-11 has 7 gas turbines in place, judging by the exhaust stacks.
368 MW for computing (was 76 MW)478 MW in all6 buildings runningBuilding 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at Socrates South and Socrates North has some outlines of gas turbines, to be installed later.
76 MW for computing99 MW in all1 building runningBuilding 4 operational. Based on our default estimate of roof-to-operational time.
No power for computing yetRoof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's unlikely to be operational.
No power for computing yetLand clearing begins for Building 1-2
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 31, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 166,015 est. | Aug 31, 2026 | Estimate |
New Albany, Ohio
Address in Epoch AI's records: 1 Community Cir, New Albany, OH 43054.
Also in Ohio
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Meta blog post with details on Prometheusengineering.fb.com
- New Albany Business Park land use mapdrive.google.com
- Letter on Socrates South Power Generation Projectdrive.google.com
- Meta Prometheus in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-prometheus