Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Core Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.sec.gov/Archives/edgar/data/1839341/000162828026030918/exhibit991polarispressre.htm
153 MW for computing (was 70 MW)181 MW in all2 buildings running - Epoch AI's projection
Estimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will likely still take several months, judging from the slow pace.
70 MW for computing98 MW in all1 building running Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.
No power for computing yetBased on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 finish seems unlikely.
No power for computing yetCore Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific says the site will provide about 70 MW of critical IT load for CoreWeave's NVIDIA GPUs.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 13, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Muskogee, Oklahoma
Address in Epoch AI's records: 1525 W 43rd St S, Muskogee, OK 74401, USA.
Also in Oklahoma
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Core Scientific ground breaking announcementinvestors.corescientific.com
- Port Muskogee ground breaking announcementportmuskogee.com
- Air quality permit applicationapplications.deq.ok.gov
- CoreWeave Muskogee OK in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-muskogee-ok