Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Buildings 7-10 are operational. Judging by their state in April 2026, we expect 3 months to finish construction and another 3 months to ramp to full capacity.
473 MW for computing (was 240 MW)662 MW in all10 buildings runningBuildings 7-10 look mostly complete, but there is still some construction work at the edges.
240 MW for computing336 MW in all6 buildings runningBuildings 3-6 are operational, based on them looking complete. DayOne reported that 390 MW is "in service" in Johor as of Jan 30. This is across both Nusajaya (including Phase 1, which we don't include here) and Kempas, but Nusajaya is the vast majority of capacity at this time. Building 7 and 8 look almost complete, while Building 9 and 10 shells are still under construction.
240 MW for computing (was 50 MW)336 MW in all6 buildings runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Oct 2, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 217,467 est. | Oct 2, 2026 | B300 based on the timing of total chip sales in the prior quarter (https://epoch.ai/data/ai-chip-sales), plus DayOne's partnership with NVIDIA (they mention using GB200 here: https://dayonedc.com/our-solutions). ByteDance likely: https://asiatimes.com/2026/03/nvidia-chip-curbs-turn-singapore-into-ai-hub-for-china/, https://english.cw.com.tw/article/article.action?id=4385. Oracle likely: https://newsletter.semianalysis.com/p/how-oracle-is-winning-the-ai-compute-market |
| H100 | Nvidia | 34,400 est. | Dec 31, 2024 | H100: https://english.cw.com.tw/article/article.action?id=4385. ByteDance likely: https://asiatimes.com/2026/03/nvidia-chip-curbs-turn-singapore-into-ai-hub-for-china/, https://english.cw.com.tw/article/article.action?id=4385. Oracle likely: https://newsletter.semianalysis.com/p/how-oracle-is-winning-the-ai-compute-market |
Johor Bahru, Johor, Malaysia
Epoch AI gives no street address for this site.
Also in Malaysia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- News of Phase 2 operationmoomoo.com
- Archived DayOne website - "120 MW in operation" in Johorweb.archive.org
- Archived DayOne website - 390 MW "in service" in Johorweb.archive.org
- Financial Times report that Alibaba and ByteDance are training AI models in southeast Asiaft.com
- DayOne Nusajaya in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/dayone-nusajaya