Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 4 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning as demonstrated by Building 1.
470 MW for computing (was 235 MW)612 MW in all4 buildings running - Epoch AI's projection
Building 2 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning, as demonstrated by Building 1. Similarly. Building 3 is expected to be commissioned now.
235 MW for computing (was 118 MW)306 MW in all2 buildings running Building 1 expected to be fully operational, assuming a 3-month fit-out period
118 MW for computing153 MW in all1 building runningLand clearing begins for Building 4.
No power for computing yetBuilding 1 being commissioned, Building 3 under construction
No power for computing yetBuilding 2 is under construction.
No power for computing yetLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Nov 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| Ascend 950PR | Huawei | 94,856 est. | Nov 1, 2026 | Cumulative count. Each new building's chip power (TDP) mirrors the mix of Huawei Ascend chip power sold in the quarter that contains the date 4 months before it came online. Q3–Q4 2026 volumes come from Epoch's Huawei roadmap report (https://epoch.ai/publications/huaweis-roadmap-to-2031) after subtracting Epoch's AI Chip Sales data for H1 2026 (https://epoch.ai/data/ai-chip-sales?view=graph&tab=h100_equivalents). Building 1's chips are assumed to have been bought around Jul 2026, when Ascend 950PR made up essentially all Huawei chip power sold (the 910C remainder was under 0.5% and is ignored). Chips = IT power ÷ the 950PR's all-in IT power per chip. The site's permitting is consistent with Ascend 950 series servers. |
Ulanqab, Inner Mongolia, China
Epoch AI gives no street address for this site.
Also in China
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Envision Galaxy Ulanqab in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/envision-galaxy-ulanqab