Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.
358 MW for computing (was 204 MW)465 MW in all6 buildings running - Epoch AI's projection
Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.
204 MW for computing (was 153 MW)266 MW in all4 buildings running We estimate Buildings 1 and 2 are operational.
153 MW for computing199 MW in all2 buildings runningBuildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.
No power for computing yetBuilding 1 and 2 under construction, with all chillers visible.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 18, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 69,074 est. | Jun 18, 2026 | Assumed based on chip ownership data, number calculated from estimated IT power |
Montgomery, Alabama
Address in Epoch AI's records: Co Rd 42, Montgomery, AL 36105, USA.
Also in Alabama
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Meta Introduction to the Montgomery Projectdatacenters.atmeta.com
- Meta expansion announcementdatacenters.atmeta.com
- Contractor announcementhenselphelps.com
- Meta Montgomery in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-montgomery