Its power over time
0 MW now, 1.07 GW planned.
Power for computing at the sites where Softbank owns the chips, month by month. After today it is Epoch AI's projection.
- Softbank
- Projected by Epoch AI
The numbers, year by year
| End of | Softbank | All |
|---|---|---|
| 2027 | 214 MW | 214 MW |
| 2028 | 1.1 GW | 1.1 GW |
| 2029 | 1.1 GW | 1.1 GW |
| Jan 2030 | 1.1 GW | 1.1 GW |
IT power. * Epoch AI's projection.
Owned · 2
Where it owns the chips.
Largest first, by power drawn now. Each opens the site's full record.
Where
In 2 places.
From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Owner means the company that owns the chips; Epoch notes it may differ from who owns or runs the building. Next change Epoch projects: OpenAI Stargate Lordstown, 214 MW by Mar 1, 2027.