Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.
333 MW for computing400 MW in all4 buildings runningBuilding 5 has more cooling towers installed but not complete, and the roof is almost complete.
333 MW for computing400 MW in all4 buildings runningWater vapor from cooling towers is present across Building 1-4, confirming their operation. Building 5 roof is still incomplete, but most backup generators and 5 cooling towers have been installed.
333 MW for computing400 MW in all4 buildings runningBuilding 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 5 roof is half complete. About half of the backup generators are in place. One cooling tower is partly built.
333 MW for computing (was 222 MW)400 MW in all4 buildings runningBuilding 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building. Building 4 still has some work around the cooling towers. Work is underway on Building 5 - some walls and a few backup generators are in place.
222 MW for computing (was 144 MW)267 MW in all3 buildings runningBuilding 2 is operational. Google Earth imagery shows 6 cooling towers installed as of 2024-04-20, and a final 7th unit appeared as of 2024-09-13, with minimal construction around the building. Building 3 roof is also complete.
144 MW for computing (was 67 MW)173 MW in all2 buildings runningBuilding 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete.
67 MW for computing80 MW in all1 building runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 18, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v6e | 262,731 est. | Oct 14, 2025 | Cumulative through Building 4 (Q3 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production shares, and per-chip TDP from Parameters. | |
| TPU v5e | 247,041 est. | Sep 13, 2024 | Cumulative through Building 2 (Q3 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production shares, and per-chip TDP from Parameters. | |
| TPU v5p | 66,612 est. | Jun 1, 2025 | Cumulative through Building 3 (Q2 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production shares, and per-chip TDP from Parameters. |
New Albany, Ohio
Address in Epoch AI's records: 1101 Beech Rd SW, New Albany, OH 43054.
Also in Ohio
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Draft basis of air permit for Google Omaha, a similar data centerdrive.google.com
- 2025 Environmental Reportsustainability.google
- Google New Albany in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-new-albany