Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.
50 MW for computing70 MW in all1 building runningHigh-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 (SemiAnalysis); this April image is our first high-resolution confirmation that the cooling is in place.
50 MW for computing70 MW in all1 building runningBy mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.
No power for computing yetLand clearing begins for northern two buildings (Building 1-2).
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 12, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 22,500 est. | Apr 15, 2026 | Estimate |
Vineland, New Jersey
Address in Epoch AI's records: 3963 S Lincoln Ave, Vineland, New Jersey.
More of Nebius's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Nebius: up to 300 MW capacity at new New Jersey data centernebius.com
- DataOne and Nebius partner for 300 MW AI data center (Data Centre Magazine)datacentremagazine.com
- Microsoft secures 100,000 NVIDIA GB300 via Nebius deal (Tom's Hardware)tomshardware.com
- DataOne CEO on first 50 MW delivery to Nebius (LinkedIn)linkedin.com
- Large data center nears completion in Vineland (Cape May County Herald)capemaycountyherald.com
- SemiAnalysis: Stop Saying Half of 2026 US Datacenter Capacity Is Cancelednewsletter.semianalysis.com
- Microsoft-Nebius New Jersey in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/microsoft-nebius-new-jersey