Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 4 operational at full capacity. This corresponds to "Phase III", which is expected to be delivered "starting in 2028". We assume it takes until the end of 2028 to reach full capacity.
528 MW for computing (was 396 MW)800 MW in all4 buildings running - Epoch AI's projection
Building 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is expected to be delivered "throughout 2027". We assume it takes until the end of 2027 to reach full capacity.
396 MW for computing (was 132 MW)600 MW in all3 buildings running Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.
132 MW for computing200 MW in all1 building runningBuilding 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2.
No power for computing yetBuilding 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet.
No power for computing yetBackup generator pads and steel framing for chillers are visible, similar to the 3D renderings.
No power for computing yetLand clearing: The former crypto mining Helios site begins converting the first building and expanding, with land cleared for additional buildings.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B200 | Nvidia | 63,151 est. | Aug 30, 2026 | GB200 NVL72 assumed from rack density specs (130-140 kW, matching NVL72). Phase I (1 building, 200 MW). Count = reported facility power / PUE / IT overhead / server power × 72. |
Afton, Texas
Address in Epoch AI's records: 984 County Road 112, Afton, TX 79220.
Also in Texas
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Galaxy Q3 financial results with power capacity timelineinvestor.galaxy.com
- Permit review with details on backup generators and power capacityrecords.tceq.texas.gov
- 3D renderings of Helios Building 1 on Galaxy's website, showing generators and chillersgalaxy.com
- TDLR record with Building 1 construction costs and end datetdlr.texas.gov
- Coreweave Helios in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-helios