5 sites
Every one in China.
Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.
- Running and growingVNET Bayin UlanqabUlanqab, China · ByteDance (possibly)221 MW now700 MW by Sep 2027
- Running and growingHuawei WuhuWuhu, China · Huawei197 MW now453 MW by Dec 2027
- Running and growingHuawei HoringerHoringer, China · Huawei170 MW now351 MW by Feb 2028
- RunningAlibaba ZhangbeiZhangbei County, Hebei, China · Alibaba169 MW now
- Running and growingEnvision Galaxy UlanqabUlanqab, Inner Mongolia, China · Owner not named118 MW now470 MW by Dec 2027
Power over time
875 MW now, 2.14 GW planned.
Power for computing at the sites in China, month by month. After today it is Epoch AI's projection.
- China
- Projected by Epoch AI
The numbers, year by year
| End of | China | All |
|---|---|---|
| 2024 | 0 MW | 0 MW |
| 2025 | 504 MW | 504 MW |
| 2026* | 1.1 GW | 1.1 GW |
| 2027* | 2.0 GW | 2.0 GW |
| 2028* | 2.1 GW | 2.1 GW |
| 2029* | 2.1 GW | 2.1 GW |
| Jan 2030* | 2.1 GW | 2.1 GW |
IT power. * Epoch AI's projection.
Who owns them
The companies here.
From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.