Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025.
88 MW for computing124 MW in all1 building runningBuilding complete and operational; full buildout reached. Sentinel-2 imagery shows the building finished with components installed and cars in the car park. Confirmed by Google's official blog post announcing the Waltham Cross data centre opening (https://blog.google/company-news/inside-google/around-the-globe/google-europe/united-kingdom/waltham-cross-data-centre/).
88 MW for computing124 MW in all1 building runningLand clearing begins (Sentinel-2 imagery).
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 23, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Shell Energy Europe, Engie
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v6e | 133,385 est. | Sep 1, 2025 | Full buildout (2025-09-01, 88.3 MW IT power). Operational status confirmed via Sentinel-2 imagery (building complete, cars in car park) and Google's official blog post announcing the site. Q3 FY25 mix for new capacity (TPU v6e 100% by power share; lagged one quarter from the operational date to account for purchase-to-operation delay) — a real, non-extrapolated quarter. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. Reconfirmed via high-resolution imagery in April 2026 with no additional capacity added. |
Cheshunt, United Kingdom
Address in Epoch AI's records: Land at Maxwell's Farm West, Great Cambridge Road, Cheshunt, EN8 8XH.
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Google — Waltham Cross data centre pagedatacenters.google
- Google opening announcement (Sept 2025)googlecloudpresscorner.com
- Project Saracen scoping report (Broxbourne planning application ref 07/18/1181/O)broxbourne.gov.uk
- Planning application description (CPRE Hertfordshire)cpreherts.org.uk
- Google Waltham Cross in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-waltham-cross