Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery. All cooling/mechanical rows are installed, with no obvious active building construction visible.
28 MW for computing40 MW in all1 building runningBased on Satellite imagery, Dalton 1 is still under construction. The building appears mostly roofed except for the entrance area, and there are no cooling units or backup generators installed yet.
No power for computing yetCore Scientific investor presentation clearly shows Dalton 1 with a cleared pad on this month for construction. Source: https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001140361-25-039864/0001140361-25-039864.pdf
No power for computing yetAccording to a few sources, Core Scientific announced that they're rebuilding their existing Dalton 1 (and we're assuming 2) datacenter to run AI using CoreWeave's GPUs, of which contract was first signed on this date. According to the press release, "The site modifications are expected to commence early in the second half of 2024 and achieve operational status in the first half of 2025."
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Feb 20, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 12,750 est. | Feb 20, 2026 | Estimate |
Dalton, Georgia
Address in Epoch AI's records: 2205 Industrial South Rd, Dalton, GA, 30721.
Also in Georgia
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Core Scientific pagecorescientific.com
- SEC filing with power utility informationinvestors.corescientific.com
- DCD articledatacenterdynamics.com
- Core Scientific presentationsec.gov
- CoreWeave Dalton 1 & 2 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-dalton-1-2