Running and growing · Ulanqab, China

VNET Bayin Ulanqab

VNET Bayin Ulanqab is an AI data center in Ulanqab, China, owned by ByteDance (possibly) and used by ByteDance (possibly). Epoch AI estimates it draws 221 MW for computing, rising to 700 MW by Sep 2027.

  • 221 MWfor computing now, #22 of the 96 Epoch AI tracks
  • 700 MWplanned by Sep 2027
  • $8.4 billionbuilt so far, Epoch AI's estimate in 2025 dollars
221 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW200 MW400 MW600 MW800 MW202520262027Mar 25, 2024: 0 MWJul 1, 2025: 38 MWNov 1, 2025: 171 MWDec 1, 2025: 221 MWSep 1, 2027: 700 MW (projected)0 MW200 MW400 MW600 MW800 MW202520262027Mar 25, 2024: 0 MWJul 1, 2025: 38 MWNov 1, 2025: 171 MWDec 1, 2025: 221 MWSep 1, 2027: 700 MW (projected)
  1. Epoch AI's projection

    Estimated: the nine-building section of the campus is projected to be fully operational by late 2027 or early 2028. VNET's eastern cluster (buildings 1-5) took roughly a year each from clearing to operational based on satellite imagery. The western cluster (buildings 6-9) was cleared in late 2024 but as of mid-2026 is not yet structurally complete, putting each on track for ~2 years from clearing to operational. Buildings 10 and 11 are projected to be completed sometime later. Comparable data centers in Ulanqab are expected to take at least 6 months per phase (China Unicom).

    700 MW for computing (was 221 MW)798 MW in all9 buildings running
  2. Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026.

    221 MW for computing252 MW in all4 buildings running
  3. Satellite imagery shows four operational buildings (1, 2, 4, 5), and the western part of campus (6, 7, 8, 9) has made significant construction progress. The foundation for the northern part of campus (10, 11) has started.

    221 MW for computing252 MW in all4 buildings running
  4. Building 4 is operational, similarly based on a 3-month fit-out period after structural completion in September, as seen from satellite imagery.

    221 MW for computing (was 171 MW)252 MW in all4 buildings running
  5. Buildings 2 and 5 are operational, based on a 3-month fit-out period after structural completion in August, as can be seen from satellite imagery. Land clearing for the northern part of campus (buildings 10 and 11) has started.

    171 MW for computing (was 38 MW)194 MW in all3 buildings running
  6. Satellite imagery shows that in total nine buildings have started construction, with building 1 being the only one operational. Buildings 2 and 5 are structurally complete, and the final roofs for buildings 3 and 4 have begun.

    38 MW for computing43 MW in all1 building running
  7. Building 1 is operational, based on a 3-month fit-out period after structural completion in April, as can be seen from satellite imagery.

    38 MW for computing43 MW in all1 building running
  8. Satellite imagery shows five buildings (1, 2, 3, 4, 5) under construction. Chillers are in place, but no roof is complete for any building.

    No power for computing yet
  9. Land clearing begins late March, as can be seen in satellite images (eastern part: buildings 1 & 2). VNET officially announces its signing ceremony with the Ulanqab municipal government and Shandong Hi-Speed Holdings.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of May 6, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

221 MWIT power, for the computersMay 6, 2026
252 MWtotal power, cooling included
700 MWIT power planned by Sep 2027
123,000computing power, counted as Nvidia H100 chips
$8.4 billioncapital cost so far: $5.8 billion for chips and computers, $2.6 billion for the buildings, power and land
$27 billioncapital cost once finished, by Sep 2027
$0.2 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

ByteDance (possibly)

Uses it

ByteDance (possibly)

Part of

10 GW Hyperscale 2.0

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
Ascend 910CHuawei161,296 est.Dec 1, 2025Ascend 910C is assumed based on it being the best and most-produced domestic chip at the time. Speculative to likely on User, given general partnership between VNET and ByteDance.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. VNET Bayin Ulanqab in Epoch AI's directoryepoch.ai
  2. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/vnet-bayin-ulanqab