Google Midlothian

Google Midlothian is an AI data center in Midlothian, Texas, owned by Google. Epoch AI estimates it draws 103 MW for computing.

  • 103 MWfor computing now, #53 of the 96 Epoch AI tracks
  • $3.9 billionbuilt so far, Epoch AI's estimate in 2025 dollars
103 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW202420252026Apr 1, 2023: 0 MWApr 19, 2026: 69 MWJul 1, 2026: 103 MW0 MW50 MW100 MW150 MW202420252026Apr 1, 2023: 0 MWApr 19, 2026: 69 MWJul 1, 2026: 103 MW
  1. Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.

    103 MW for computing (was 69 MW)123 MW in all1 building running
  2. Building 1 is probably mostly operational despite some cooling towers yet to be installed. In the original building permit Google only expected to build 6 new cooling towers, but they've extended the row further. This might be to support new chips with denser power configurations. Across the road, you can see the beginnings of land development for what is likely an expansion of the site, but we don't have any details on it yet.

    69 MW for computing82 MW in all1 building running
  3. Building 1 roof is complete.

    No power for computing yet
  4. Land clearing begins for Building 1.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Jul 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

103 MWIT power, for the computersJul 1, 2026
123 MWtotal power, cooling included
103 MWthe most Epoch AI projects here
144,000computing power, counted as Nvidia H100 chips
$3.9 billioncapital cost so far: $2.7 billion for chips and computers, $1.2 billion for the buildings, power and land
$3.9 billioncapital cost, finished
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
TPU v7Google48,994 est.Jul 1, 2026Cumulative total after the expanded cooling row is completed; added capacity uses the Q2 FY26 mix (lagged one quarter from the date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
TPU v6eGoogle31,636 est.Jul 1, 2026Cumulative total after the expanded cooling row is completed; added capacity uses the Q2 FY26 mix (lagged one quarter from the date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Site Map and Permitecode360.com
  2. City Council Presentationarchive-stream.granicus.com
  3. Google Midlothian in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-midlothian