Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.
103 MW for computing (was 69 MW)123 MW in all1 building runningBuilding 1 is probably mostly operational despite some cooling towers yet to be installed. In the original building permit Google only expected to build 6 new cooling towers, but they've extended the row further. This might be to support new chips with denser power configurations. Across the road, you can see the beginnings of land development for what is likely an expansion of the site, but we don't have any details on it yet.
69 MW for computing82 MW in all1 building runningBuilding 1 roof is complete.
No power for computing yetLand clearing begins for Building 1.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v7 | 48,994 est. | Jul 1, 2026 | Cumulative total after the expanded cooling row is completed; added capacity uses the Q2 FY26 mix (lagged one quarter from the date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v6e | 31,636 est. | Jul 1, 2026 | Cumulative total after the expanded cooling row is completed; added capacity uses the Q2 FY26 mix (lagged one quarter from the date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Midlothian, Texas
Address in Epoch AI's records: 3250 Railport Parkway, Midlothian, TX 76065.
Also in Texas
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Site Map and Permitecode360.com
- City Council Presentationarchive-stream.granicus.com
- Google Midlothian in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-midlothian