Running · Toney, Alabama

Meta Huntsville

Meta Huntsville is an AI data center in Toney, Alabama, owned by Meta and used by Meta. Epoch AI estimates it draws 146 MW for computing.

  • 146 MWfor computing now, #41 of the 96 Epoch AI tracks
  • $5.5 billionbuilt so far, Epoch AI's estimate in 2025 dollars
146 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW20222023202420252026Dec 13, 2021: 0 MWMar 4, 2026: 78 MWJun 2, 2026: 146 MW0 MW50 MW100 MW150 MW200 MW20222023202420252026Dec 13, 2021: 0 MWMar 4, 2026: 78 MWJun 2, 2026: 146 MW
  1. We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.

    146 MW for computing (was 78 MW)198 MW in all2 buildings running
  2. We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.

    78 MW for computing105 MW in all1 building running
  3. Color artifacts appear on small number of Building 1 fans. Continued presence of construction equipment and unfinished land around Building 2 suggests the final phase of construction.

    No power for computing yet
  4. We believe Building 1 and 2 are still being finished due to continued construction vehicles and unfinished land around the data center sites.

    No power for computing yet
  5. Building 2 roof starts to go on and its cooling installation is in progress.

    No power for computing yet
  6. Building 1 land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Jun 2, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

146 MWIT power, for the computersJun 2, 2026
198 MWtotal power, cooling included
146 MWthe most Epoch AI projects here
167,000computing power, counted as Nvidia H100 chips
$5.5 billioncapital cost so far: $3.8 billion for chips and computers, $1.7 billion for the buildings, power and land
$5.5 billioncapital cost, finished
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Meta

Uses it

Meta

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Tennessee Valley Authority, NextEra Energy Resources, First Solar

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
B300Nvidia66,004 est.Jun 2, 2026Estimate
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Announcement of expansion completing in 2026plateauexcavation.com
  2. TVA solar installation announcementsprnewswire.com
  3. Meta Huntsville in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-huntsville