Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 6-14 are operational (estimate). Buildings 1-4 took an estimated 2.25 years on this site. We assume Buildings 6-14 get underway by July 2026, and take the same time as Buildings 1-4. This is later than the expected completion by 2027.
840 MW for computing (was 284 MW)1.01 GW in all14 buildings running - Epoch AI's projection
Building 5 is operational (estimate).
284 MW for computing (was 228 MW)341 MW in all5 buildings running Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.
228 MW for computing273 MW in all4 buildings runningRoof complete on Buildings 3
No power for computing yetLand clearing begins
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 15, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| Trainium2 | Amazon | 261,244 est. | May 15, 2026 | Chip type assumed from Project Rainier announcement (Trainium2). 4 buildings (type 1, 26 generators each) operational. Count = buildings × chips per building, where chips per building = generator-based power / (PUE × IT overhead × chip TDP). |
Ridgeland, Mississippi
Address in Epoch AI's records: 1626 County Line Road Ridgeland, Mississippi.
Also in Mississippi
More of Amazon's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Air Construction Permitdrive.google.com
- Permit review documentdrive.google.com
- Backup diesel generator referenced in the permitcat.com
- New York Times article on Project Rainiernytimes.com
- Amazon Ridgeland in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/amazon-ridgeland