AI data centers by US state

AI data centers in Pennsylvania.

Epoch AI tracks 2 of its 96 large AI data centers in Pennsylvania, drawing 108 MW for computing now and 261 MW once the projects there finish. Owners: Amazon, CoreWeave.

  • 2AI data centers tracked
  • 108 MWfor computing now, #25 of 40 places
  • 261 MWplanned, if every project finishes
2 sites

Every one in Pennsylvania.

Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.

  1. Running and growingAWS BerwickBerwick, Pennsylvania · Amazon108 MW now169 MW by Aug 2027
  2. Being builtCoreWeave Lancaster Greenfield siteLancaster, Pennsylvania · CoreWeaveNot drawing power yet92 MW by Jun 2027
Power over time

108 MW now, 261 MW planned.

Power for computing at the sites in Pennsylvania, month by month. After today it is Epoch AI's projection.

  • Pennsylvania
  • Projected by Epoch AI
00.25 GW0.5 GW20262027202820292030TodayProjected
The numbers, year by year
End ofPennsylvaniaAll
202547 MW47 MW
2026*108 MW108 MW
2027*261 MW261 MW
2028*261 MW261 MW
2029*261 MW261 MW
Jan 2030*261 MW261 MW

IT power. * Epoch AI's projection.

Who owns them

The companies here.

From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.