Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the number of generators reported in an air quality permit application (p.92-93). The dry cooler array is more than double the size of the Building 1 array, which suggests an even larger power capacity than we estimate, but we believe the generator-based estimate is more reliable here.
300 MW for computing (was 161 MW)389 MW in all3 buildings running Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.
161 MW for computing214 MW in all2 buildings runningBuilding 3 foundation is underway. Building 2 exterior looks totally clean/landscaped.
161 MW for computing214 MW in all2 buildings runningBuilding 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front.
161 MW for computing (was 81 MW)214 MW in all2 buildings runningBuilding 2 now has generators in place, but there is still a crane and construction work present.
81 MW for computing107 MW in all1 building runningBuilding 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed.
81 MW for computing107 MW in all1 building runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 13, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v6e | 98,179 est. | Jun 30, 2025 | Building 2 (Q2 FY25 mix for new capacity: v6e + v5p; lagged one quarter from the operational date to account for purchase-to-operation delay). Delta from Building 1 IT power. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5e | 153,165 est. | Aug 30, 2023 | Building 1 expansion (Q3 FY23 mix for new capacity: v5e + v4; lagged one quarter from the operational date to account for purchase-to-operation delay), assuming it was fully retrofitted. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 16,521 est. | Jun 30, 2025 | Building 2 (Q2 FY25 mix for new capacity: v6e + v5p; lagged one quarter from the operational date to account for purchase-to-operation delay). Delta from Building 1 IT power. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v4 | 34,609 est. | Aug 30, 2023 | Building 1 expansion (Q3 FY23 mix for new capacity: v5e + v4; lagged one quarter from the operational date to account for purchase-to-operation delay), assuming it was fully retrofitted. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Clark, Nevada
Epoch AI gives no street address for this site.
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Air quality permit application listing emergency generators and a small "R&D" fuel cell plantndep-onbase.nv.gov
- Aterioaterio.io
- Google data center pagedatacenters.google
- Google Storey County in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-storey-county