Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 3 is operational, based off of colored motion artifacts from cooling towers.
238 MW for computing (was 174 MW)286 MW in all3 buildings runningBuilding 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
174 MW for computing (was 87 MW)208 MW in all2 buildings runningBuilding 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
87 MW for computing104 MW in all1 building runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of May 20, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v7 | 34,087 est. | May 20, 2026 | Estimate | |
| TPU v6e | 66,108 est. | May 20, 2026 | Building 3 (Q2 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). In addition to Buildings 1 and 2 with same methodology. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5e | 259,473 est. | Apr 29, 2025 | Building 2 (Q1 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). In addition to Building 1. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 37,789 est. | Apr 29, 2025 | Estimate |
Bristow, Virginia
Address in Epoch AI's records: 13001 Rollins Ford Road, Bristow, VA 20136.
Also in Virginia
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Google Environmental Reportsustainability.google
- Google Bristow in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-bristow