Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Building 4.
395 MW for computing (was 316 MW)474 MW in all5 buildings running - Epoch AI's projection
Building 4 is operational. Expect a 4th building because there's enough land cleared for it. Assuming the foundation starts at the end of May 2026 and it takes a similar time to Building 3 from foundation to operational (1 year 8 months).
316 MW for computing (was 237 MW)379 MW in all4 buildings running Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
237 MW for computing (was 158 MW)284 MW in all3 buildings runningBuilding 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.
158 MW for computing189 MW in all2 buildings runningBuilding 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.
158 MW for computing189 MW in all2 buildings runningConfident that Building 2 is operational
158 MW for computing189 MW in all2 buildings runningConfirmation that there's no obvious construction happening for Building 2. Building 3 roof started.
158 MW for computing189 MW in all2 buildings runningBuilding 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).
158 MW for computing (was 79 MW)189 MW in all2 buildings runningBuilding 2 has 3 cooling towers installed.
79 MW for computing95 MW in all1 building runningBuilding 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.
79 MW for computing95 MW in all1 building runningLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v7 | 41,901 est. | Jun 30, 2026 | Building 3 (Q2 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Buildings 4 and 5 are omitted because their lagged quarters (Q4 FY27, Q2 FY28) are extrapolated with no per-version mix. Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5e | 263,957 est. | Nov 19, 2024 | Cumulative through Building 2 (Q4 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v6e | 28,846 est. | Jun 30, 2026 | Cumulative through Building 3 (Q2 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 47,061 est. | Nov 19, 2024 | Cumulative through Building 2 (Q4 FY24 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Omaha, Nebraska
Address in Epoch AI's records: 11110 State St, Omaha, NE 68142.
Also in Nebraska
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Draft basis of air permit with details of cooling towersdrive.google.com
- 2025 Environmental Reportsustainability.google
- Google Omaha in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-omaha