Google Red Oak

Google Red Oak is an AI data center in Red Oak, Texas, owned by Google. Epoch AI estimates it draws 77 MW for computing, rising to 154 MW by Dec 2026.

  • 77 MWfor computing now, #59 of the 96 Epoch AI tracks
  • 154 MWplanned by Dec 2026
  • $2.9 billionbuilt so far, Epoch AI's estimate in 2025 dollars
77 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW200 MW202420252026Apr 30, 2023: 0 MWAug 25, 2025: 77 MWDec 1, 2026: 154 MW (projected)0 MW50 MW100 MW150 MW200 MW202420252026Apr 30, 2023: 0 MWAug 25, 2025: 77 MWDec 1, 2026: 154 MW (projected)
  1. Epoch AI's projection

    Building 2 is estimated to be operational.

    154 MW for computing (was 77 MW)185 MW in all2 buildings running
  2. Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.

    77 MW for computing93 MW in all1 building running
  3. Building 1 is operational, based on a Google Earth image showing a completed building shell and equipment, and the large construction car park being emptied. Building 2 shell looks mostly completed.

    77 MW for computing93 MW in all1 building running
  4. First signs of development/land clearing

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Feb 6, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

77 MWIT power, for the computersFeb 6, 2026
93 MWtotal power, cooling included
154 MWIT power planned by Dec 2026
108,000computing power, counted as Nvidia H100 chips
$2.9 billioncapital cost so far: $2.0 billion for chips and computers, $0.9 billion for the buildings, power and land
$5.8 billioncapital cost once finished, by Dec 2026
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
TPU v6eGoogle116,560 est.Aug 25, 2025Building 1 (Q3 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and per-chip TDP.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Media coverage confirming location, project name, investment size, and some timingmysanantonio.com
  2. Google PUE data listing the Red Oak site from Q1 2026datacenters.google
  3. Google Red Oak in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-red-oak