14 sites
Every one in Texas.
Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.
- RunningOpenAI Stargate AbileneAbilene, Texas · Oracle824 MW now
- Running and growingCoreWeave Denton TXDenton, Texas · CoreWeave262 MW now282 MW by May 2027
- RunningMeta TempleTemple, Texas · Meta178 MW now
- Running and growingCoreweave HeliosAfton, Texas · CoreWeave132 MW now528 MW by Jan 2029
- RunningGoogle MidlothianMidlothian, Texas · Google103 MW now
- Running and growingGoogle Red OakRed Oak, Texas · Google77 MW now154 MW by Dec 2026
- RunningMicrosoft SAT40San Antonio, Texas · Microsoft75 MW now
- RunningMicrosoft SAT14San Antonio, Texas · Microsoft47 MW now
- Running and growingVantage TX1San Antonio, Texas · Owner not named32 MW now128 MW by Aug 2027
- Being builtOpenAI Stargate ShackelfordAbilene, Texas · OracleNot drawing power yet1.40 GW by Nov 2028
- Being builtGoodnightClaude, Texas · Google (possibly)Not drawing power yet1.01 GW by Oct 2027
- Being builtOpenAI Stargate MilamBurlington, Texas · SoftbankNot drawing power yet857 MW by Dec 2028
- Being builtCrusoe Abilene ExpansionAbilene, Texas · MicrosoftNot drawing power yet672 MW by Nov 2027
- Being builtAnthropic Barber LakeColorado City, Texas · Cipher MiningNot drawing power yet207 MW by Apr 2027
Power over time
1.73 GW now, 6.46 GW planned.
Power for computing at the sites in Texas, month by month. After today it is Epoch AI's projection.
- Texas
- Projected by Epoch AI
The numbers, year by year
| End of | Texas | All |
|---|---|---|
| 2024 | 66 MW | 66 MW |
| 2025 | 596 MW | 596 MW |
| 2026* | 2.0 GW | 2.0 GW |
| 2027* | 4.2 GW | 4.2 GW |
| 2028* | 6.3 GW | 6.3 GW |
| 2029* | 6.5 GW | 6.5 GW |
| Jan 2030* | 6.5 GW | 6.5 GW |
IT power. * Epoch AI's projection.
Who owns them
The companies here.
Google · 3Microsoft · 3Oracle · 2CoreWeave · 2Meta · 1Softbank · 1Cipher Mining · 1Every state and country
From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.