Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 4 and supporting facilities/buildings operational, whole facility now operational. Based on the environmental analysis (page 6) filed for the site.
902 MW for computing1.30 GW in all4 buildings running Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
No power for computing yetLand clearing continues, foundation construction clearly begins for eastern and northern buildings (Building 1-2)
No power for computing yetGround broken for the facility, land clearing begins for all buildings
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 24, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Port Washington, Wisconsin
Epoch AI gives no street address for this site.
Also in Wisconsin
More of Oracle's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Data center page on Vantage websitevantage-dc.com
- Environmental Analysis Summarydrive.google.com
- OpenAI Stargate Wisconsin in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-wisconsin