4 sites
Every one in Iowa.
Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.
- RunningGoogle Council Bluffs (East)Council Bluffs, Iowa · Google237 MW now
- RunningMicrosoft Project OsmiumCumming, Iowa · Microsoft190 MW now
- Being builtQTS Cedar RapidsFairfax, Iowa · Meta (possibly)Not drawing power yet1.13 GW by Nov 2027
- Being builtGoogle Cedar RapidsCedar Rapids, Iowa · GoogleNot drawing power yet261 MW by May 2027
Power over time
427 MW now, 1.82 GW planned.
Power for computing at the sites in Iowa, month by month. After today it is Epoch AI's projection.
- Iowa
- Projected by Epoch AI
The numbers, year by year
| End of | Iowa | All |
|---|---|---|
| 2021 | 48 MW | 48 MW |
| 2022 | 48 MW | 48 MW |
| 2023 | 95 MW | 95 MW |
| 2024 | 174 MW | 174 MW |
| 2025 | 348 MW | 348 MW |
| 2026* | 962 MW | 962 MW |
| 2027* | 1.8 GW | 1.8 GW |
| 2028* | 1.8 GW | 1.8 GW |
| 2029* | 1.8 GW | 1.8 GW |
| Jan 2030* | 1.8 GW | 1.8 GW |
IT power. * Epoch AI's projection.
Who owns them
The companies here.
From Epoch AI's AI data centers data (CC BY 4.0), read Nov 25, 2026. Epoch tracks the largest sites, mostly those that came online from 2024, so smaller data centers here aren't counted.