Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
We estimate that Building 1 will be operational by Summer 2027 due to third party reporting.
92 MW for computing124 MW in all1 building running Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 13, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Lancaster, Pennsylvania
Address in Epoch AI's records: 216 Greenfield Rd, Lancaster, PA.
Also in Pennsylvania
More of CoreWeave's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- CoreWeave announces plans to spend $6 billion on Lancaster data centersinvestors.coreweave.com
- Machine Investment Group purchases two former printing press sites in Lancaster, Pennsylvaniadatacenterdynamics.com
- CoreWeave Lancaster Greenfield site in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/coreweave-lancaster-greenfield-site