Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Expect Building 4-6 have finished upgrading with new chillers.
169 MW for computing (was 85 MW)203 MW in all6 buildings runningChillers look fully installed on Building 4-6. Some chillers on Building 4 and 5 appear to have snow in the fan holes, suggesting they are not operating and other chillers are operating (since warm air would melt the snow). There is still a bit of construction equipment around Building 6 so it may not be quite operational.
85 MW for computing102 MW in all3 buildings runningLarge substation is visibly connected to transmission lines. New chillers look fully installed on Building 1-3. Since power and cooling is apparently in place, we expect Building 1-3 are operational. Chillers are almost installed on Building 4-6, with construction equipment still around the building.
85 MW for computing102 MW in all3 buildings runningConstruction starts, with groundwork visible around Buildings 1-4.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jan 3, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| H20 | Nvidia | 213,211 est. | Jan 3, 2026 | Assume Nvidia H20 because it had the biggest volume of any AI chip available in China by unit count, Alibaba is unlikely to use Huawei chips, and H20s are available on Alibaba cloud (https://web.archive.org/web/20250923164329/https://www.alibabacloud.com/help/en/ecs/user-guide/gpu-accelerated-compute-optimized-and-vgpu-accelerated-instance-families-1). Assume the same chip-to-IT power multiplier as the DGX H100. SemiAnalysis estimated 11112W per H100 DGX including networking (https://newsletter.semianalysis.com/p/ai-datacenter-energy-dilemma-race), compared to 700W per chip, with 8 chips per DGX. |
Zhangbei County, Hebei, China
Address in Epoch AI's records: Alibaba Zhangbei Yun Calculation Data Center, Zhangbei County, Zhangjiakou, Hebei, China, 076471.
Also in China
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Alibaba Zhangbei in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/alibaba-zhangbei