AI data centers in Finland.

Epoch AI tracks 1 of its 96 large AI data centers in Finland, drawing 75 MW for computing now and 145 MW once the projects there finish. Owners: Nebius.

  • 1AI data center tracked
  • 75 MWfor computing now, #28 of 40 places
  • 145 MWplanned, if every project finishes
1 site

Every one in Finland.

Largest first, by power drawn now. Each opens the site's full record: owner, users, chips, cost and how it was built.

  1. Running and growingNebius MantsalaMäntsälä, Uusimaa, Finland · Nebius75 MW now145 MW by Dec 2027
Power over time

75 MW now, 145 MW planned.

Power for computing at the sites in Finland, month by month. After today it is Epoch AI's projection.

  • Finland
  • Projected by Epoch AI
00.25 GW202520262027202820292030TodayProjected
The numbers, year by year
End ofFinlandAll
202440 MW40 MW
202540 MW40 MW
2026*75 MW75 MW
2027*145 MW145 MW
2028*145 MW145 MW
2029*145 MW145 MW
Jan 2030*145 MW145 MW

IT power. * Epoch AI's projection.

Who owns them