Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see Cipher 2025-11-20 PR). We estimate ~Apr 2027, about 3 months later than the ~Q1 2027 target, based on construction progress.
207 MW for computing (was 168 MW)300 MW in all1 building running - Epoch AI's projection
Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the site is shell-complete but not yet energized as of the Jul 2026 image. Disclosed target: Cipher 2025-09-25 PR states the 168 MW critical IT load is "expected to be delivered by September 2026."
168 MW for computing244 MW in all1 building running Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.
No power for computing yetFoundations of Building 1 are visible.
No power for computing yetSite grading and civil works begin.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
No wider project named
Not named
Not named
Not named
Colorado City, Texas
Epoch AI gives no street address for this site.
Also in Texas
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Cipher signs 168 MW AI hosting deal with Fluidstack, Google backs it (Sep 2025)globenewswire.com
- Cipher adds 56 MW gross to reach 300 MW at Barber Lake (Nov 2025)globenewswire.com
- Cipher 8-K exhibit: 207 MW total critical IT load (SEC, Nov 2025)sec.gov
- Anthropic to expand use of Google Cloud TPUs (Oct 2025)googlecloudpresscorner.com
- Anthropic $50B US AI infrastructure with Fluidstack (Nov 2025)anthropic.com
- DCD: Cipher secures Fluidstack as customer, Google as investordatacenterdynamics.com
- Air quality permit listing 60 x 3 MW plus 60 x 3.1MW backup generatorsdrive.google.com
- Anthropic Barber Lake in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/anthropic-barber-lake