Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.
824 MW for computing (was 618 MW)1.15 GW in all8 buildings runningBuildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer" (transcript). 618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier. Since Oracle is the chip owner rather than the facility operator, we assume "delivered" means the chips are installed and ready to use.
618 MW for computing (was 412 MW)865 MW in all6 buildings runningBuildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.
412 MW for computing577 MW in all4 buildings runningBuildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.
412 MW for computing (was 206 MW)577 MW in all4 buildings runningBuilding 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete.
206 MW for computing288 MW in all2 buildings runningThe 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building 4 has about 80% of chillers installed. Other buildings have few or no chillers installed.
206 MW for computing288 MW in all2 buildings runningBuilding 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also consistent with satellite imagery. By January 15, Building 2 looked as finished as Building 1, whereas on September 26 it did not look finished.
206 MW for computing (was 103 MW)288 MW in all2 buildings runningBuilding 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm that both buildings are fully operational. The announcement also stated that "Oracle began delivering the first NVIDIA GB200 racks in June", and we think 3 months is enough time to ram to 50,000 GB200s in Building 1. The satellite image also suggests that Building 1 is complete (shell and equipment done, many cars neatly parked) while Building 2 is ongoing (trucks and construction equipment still present). The 200 MW substation built in 2022 and expanded in 2024 is enough to power both buildings. To the right of Building 2, five gas turbines are in place with five more turbines still under construction. Chillers are partly installed for Building 3. Roof is complete for Building 4. The larger 1 GW substation is not complete yet.
103 MW for computing144 MW in all1 building runningBuilding 1 looks close to finishing construction, with chillers in place. OpenAI stated that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenant improvement" work is not due until September, however.
No power for computing yetLand clearing begins for northern two buildings (Building 1-2)
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Nov 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 302,400 est. | Nov 1, 2026 | Buildings 7-8 come online, bringing total B300 buildings to 6. Same building design as B200 buildings but slightly larger chillers suggest same server count with higher power per server, consistent with B300 and timing of B300 chip sales ramp. |
| B200 | Nvidia | 100,800 disclosed | Dec 24, 2025 | Crusoe Impact Report 2024, p.19 |
Abilene, Texas
Address in Epoch AI's records: 5502 Spinks Rd, Abilene, TX 79601.
Also in Texas
More of Oracle's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Crusoe 2024 Impact Report, with details on Abilenedrive.google.com
- Air Permit Application for buildings 1-2, featuring blueprints on p.157drive.google.com
- Mortensen’s profile of the project, with details of substationsmortenson.com
- OpenAI Stargate Abilene in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/openai-stargate-abilene