Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Buildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project.
422 MW for computing (was 163 MW)570 MW in all4 buildings running - Epoch AI's projection
Building 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1.
163 MW for computing (was 86 MW)220 MW in all2 buildings running - Epoch AI's projection
Building 1 is operational, based on a 5 month extrapolation from its roof completion date.
86 MW for computing117 MW in all1 building running Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.
No power for computing yetBuildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowling Substation, an existing substation to the northeast of the data center, appear complete.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jul 30, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Being built under construction, not yet drawing power for computing.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Bowling Green, Ohio
Address in Epoch AI's records: 12356 Middleton Pike, Bowling Green, OH 43402.
Also in Ohio
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Meta letter to Middleton Townshipdrive.google.com
- Construction notice for new transmission lines to data center substationdrive.google.com
- Ohio Power Siting Board announcementarchive.ph
- Apollo Power Generation Project Letter of Notice Appendix A, with a project timelinedrive.google.com
- Meta Bowling Green in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-bowling-green