Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Buildings 7-8 assumed operational. These buildings were roofed by March 2026 and by August 2026 their cooling and backup power equipment looked complete. With an additional two months of commissioning after August we approximate their operability to this date.
422 MW for computing (was 322 MW)590 MW in all9 buildings runningBuildings 5-6 assumed operational. These buildings were roofed between Sep and Dec 2025 and equipment fit-out was underway in Jan 2026; applying the default roof-to-operational delay plus ramp time approximates their operability to this date.
322 MW for computing (was 223 MW)451 MW in all7 buildings runningBuildings 5-6 look complete and parking lot activity suggests they are nearly operational. Building 7-8 nearing completion with some construction equipment still in their vicinity.
223 MW for computing313 MW in all5 buildings runningBuildings 1-4 and the smaller Building 9 assumed fully operational: cooling equipment was installed by Jan 2026 (Building 9 on the same timeline as Building 1) and the implied KTP in-service figure (~80 MW) shows them ramping in early 2026, so we allow ~3 more months to reach full capacity. Rooftop equipment texture is visible campus-wide.
223 MW for computing (was 80 MW)313 MW in all5 buildings runningBuildings 3 and 4 are operational. This is based on construction looking complete, and DayOne reporting 390 MW "in service" across both Nusajaya and Kempas campuses as of Jan 30. Subtracting our Nusajaya estimates (69.5 MW excluded in Phase 1 + 240.3 MW AI) implies ~80 MW in service at KTP, consistent with roughly 2 buildings per our ~49.6 MW per-building estimate, but not at full capacity. Buildings 1 and 2 look complete with rooftop cooling equipment installed (32 units each, in 2 strips of 16). The units are almost all single-fan cells; Building 2 has one strip of 16 single-fan cells and one darker bank of 16 long multi-fan air-cooled (slat) units - this suggests an cell-to-air-cooled power equivalence that informs our power estimates. The smaller Building 9 (west of Building 1, half fit-out: 16 cells) also has its cooling installed. Building 5 has rooftop equipment partially installed; Building 6 is roofed; Buildings 7-8 shells are still underway.
80 MW for computing112 MW in all2 buildings runningIn this video at 6:28, some fans can be seen in motion for Building 3. However, we think it's unlikely that any buildings are at fully operational capacity yet. Buildings 1-4 are roofed. Building 5-6 shells are underway.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Oct 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not named by Epoch AI
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 190,237 est. | Oct 1, 2026 | B300 based on the timing of total chip sales in the prior quarter (https://epoch.ai/data/ai-chip-sales), plus DayOne's partnership with NVIDIA (they mention using GB200 here: https://dayonedc.com/our-solutions). Owners carried over from our Nusajaya sheet; as of Jul 2026 we found no Kempas-specific tenant reporting. ByteDance likely: https://asiatimes.com/2026/03/nvidia-chip-curbs-turn-singapore-into-ai-hub-for-china/, https://english.cw.com.tw/article/article.action?id=4385. Oracle likely: https://newsletter.semianalysis.com/p/how-oracle-is-winning-the-ai-compute-market |
Johor Bahru, Johor, Malaysia
Address in Epoch AI's records: HP79+MP, 81300 Johor Bahru, Johor, Malaysia.
Also in Malaysia
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- News of Phase 2 operationmoomoo.com
- Archived DayOne website - "120 MW in operation" in Johorweb.archive.org
- Archived DayOne website - 390 MW "in service" in Johorweb.archive.org
- Financial Times report that Alibaba and ByteDance are training AI models in southeast Asiaft.com
- DayOne Kempas in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets