Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.
152 MW for computing198 MW in all2 buildings runningBuilding 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the following week.
No power for computing yetLand clearing begins.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Jun 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| B300 | Nvidia | 68,571 est. | Jun 1, 2026 | Presumably the same as Meta Temple, and the most sold chip in Q4 2025 by a small margin. |
Kuna, Idaho
Address in Epoch AI's records: 601 Kuna Mora Rd, Kuna ID 83634.
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Official Pamphlet from Metadatacenters.atmeta.com
- Application for Power Purchase Agreement, Pleasant Valley Solar 1puc.idaho.gov
- Application for Power Purchase Agreement, Pleasant Valley Solar 2lf-puc.idaho.gov
- Approval to move start date of Solar 2 to May 31, 2026puc.idaho.gov
- staff commentslf-puc.idaho.gov
- Notice of Application for 3rd PPA (Blacks Creek Energy Center)puc.idaho.gov
- Idaho Statesman: Peak construction reached in March 2025idahostatesman.com
- Idaho Statesman: Expected water usage reported in 2022idahostatesman.com
- Meta Kuna in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-kuna