Intelligence Progress
Running · Kansas City, Missouri

Google Kansas City East

Google Kansas City East is an AI data center in Kansas City, Missouri, owned by Google. Epoch AI estimates it draws 105 MW for computing.

  • 105 MWfor computing now, #52 of the 96 Epoch AI tracks
  • $4.0 billionbuilt so far, Epoch AI's estimate in 2025 dollars
105 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW50 MW100 MW150 MW202420252026Dec 1, 2023: 0 MWAug 1, 2026: 105 MW0 MW50 MW100 MW150 MW202420252026Dec 1, 2023: 0 MWAug 1, 2026: 105 MW
  1. Building 1 operational. Estimated based on present construction progress and typical timelines.

    105 MW for computing126 MW in all1 building running
  2. Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, and construction has started on generators and cooling. A clear foundation has been cleared for Building 4, though no construction has begun.

    No power for computing yet
  3. Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finished as well.

    No power for computing yet
  4. Foundation work begins for Building 3. Building 1 generators seem complete.

    No power for computing yet
  5. Foundation work begins on Building 2. Building 1 roof is fully black.

    No power for computing yet
  6. Foundation work begins on Building 1

    No power for computing yet
  7. Land clearing begins.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Aug 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

105 MWIT power, for the computersAug 1, 2026
126 MWtotal power, cooling included
105 MWthe most Epoch AI projects here
203,000computing power, counted as Nvidia H100 chips
$4.0 billioncapital cost so far: $2.7 billion for chips and computers, $1.2 billion for the buildings, power and land
$4.0 billioncapital cost, finished
$0.1 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Google

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Hunt Midwest Business Center press release linking data center with Googlehuntmidwest.com
  2. DCD article on the sitedatacenterdynamics.com
  3. Google Kansas City East in Epoch AI's directoryepoch.ai
  4. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-kansas-city-east