Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
All four buildings are operational.
180 MW for computing243 MW in all4 buildings runningAll four buildings are operational
180 MW for computing243 MW in all4 buildings runningWe believe Buildings 2, 3, and 4 are operational due to the absence of construction vehicles and completed parking lots/concrete around the facilities. There is also a vehicle presence in the parking lot similar to the level seen during normal operation at other data center campuses. Finally, it is more than 12 months after cooling has been installed or in the final stages of install for the remaining three buildings.
180 MW for computing (was 45 MW)243 MW in all4 buildings runningSatellite imagery shows Building 2 and 3 cooling nearing completion and Building 4 cooling install continues. We believe Building 1 is operational now due to the lack of construction equipment on or immediately around the building.
45 MW for computing61 MW in all1 building runningSatellite imagery shows Building 3 and 4 cooling start to go on.
No power for computing yetFirst signs of site land clearing appear on satellite imagery.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Apr 17, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running drawing power now, with no further growth in Epoch AI's projection.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| H100 | Nvidia | 123,839 est. | Nov 8, 2024 | H100 DGX assumed from installation of all cooling by end of 2023. Count = Total IT power / IT overhead / server power x 8 |
Hillsboro, Oregon
Address in Epoch AI's records: 4755 NE Huffman St, Hillsboro, OR 97124.
Also in Oregon
More of Meta's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- QTS Hillsboro 2 data center announcementq.com
- QTS and Meta sign an agreement with PGE for a 120MWac solar installationq.com
- Meta-QTS Hillsboro 2 in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/meta-qts-hillsboro-2