Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
Building 5 operational. The transmission line construction notice that expands site by 100 MW is assumed to be entirely for Building 5, and has an in-service date of July 1, 2027 (page 3). Estimate taken on the safe side based on completion times for Building 3-4 from when roof was complete.
386 MW for computing (was 303 MW)464 MW in all5 buildings running Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.
303 MW for computing364 MW in all4 buildings runningBuilding 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
303 MW for computing (was 216 MW)364 MW in all4 buildings runningBuildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).
216 MW for computing260 MW in all3 buildings runningBuilding 3 operational. Surrounding roads finished, no more visible construction.
216 MW for computing (was 130 MW)260 MW in all3 buildings runningBuilding 2 operational. Parking complete, no more visible construction.
130 MW for computing (was 65 MW)156 MW in all2 buildings runningBuilding 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.
65 MW for computing78 MW in all1 building runningBuilding 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.
No power for computing yetLand clearing begins on the eastern half of the site, for Buildings 1-2
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Aug 5, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Google DeepMind (possibly)
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| TPU v6e | 204,638 est. | May 1, 2026 | Cumulative through Building 4 (Q1 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v7 | 38,886 est. | May 1, 2026 | Building 4 (Q1 FY26 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5e | 193,949 est. | Mar 1, 2025 | Cumulative through Building 2 (Q1 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. | |
| TPU v5p | 28,246 est. | Mar 1, 2025 | Cumulative through Building 2 (Q1 FY25 mix for new capacity; lagged one quarter from the operational date to account for purchase-to-operation delay). Chip type and quantity derived from Timeline power, TPU_Production power shares, and Parameters TDP. |
Columbus, Ohio
Address in Epoch AI's records: 5076 S High St, Columbus, OH 43207.
Also in Ohio
More of Google's
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- DCD article detailing early work beginning on the sitedatacenterdynamics.com
- Transmission line construction notice; details current site capacity, expansion, and maximum future site capacityaeptransmission.com
- Google Columbus in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/google-columbus