Watched from above.
Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.
- Epoch AI's projection
All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is excluded due to insufficient cooling. The time from observed land-clearing to operational is 23-26 months based on previous buildings. As with the other buildings, we assume 65% rack occupancy.
453 MW for computing (was 360 MW)589 MW in all8 buildings running - Epoch AI's projection
Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is about 3.7x more power than one of the previous buildings, based on the size and quantity of cooling and backup generator equipment observed in satellite imagery. As with the other buildings, we assume 65% rack occupancy.
360 MW for computing (was 197 MW)468 MW in all6 buildings running Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.
197 MW for computing (was 156 MW)256 MW in all5 buildings runningOn the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in approximately one month, given that it is structurally complete and 75% of its cooling looks to be installed. On the east campus, building 9 is under construction.
156 MW for computing202 MW in all4 buildings runningFour buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining.
156 MW for computing202 MW in all4 buildings runningFour buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have sufficient cooling for AI despite its backup generators. The remaining three buildings, one per campus, have not begun construction.
156 MW for computing202 MW in all4 buildings runningFour buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.
156 MW for computing (was 118 MW)202 MW in all4 buildings runningThree buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but as of 2026 does not have the cooling sufficient for AI. Assumes a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.
118 MW for computing (was 44 MW)153 MW in all3 buildings runningThe first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. We multiply each building's estimated capacity by an assumed 65% rack occupancy rate. This is close to the ~62–64% reported for Wuhu and other national data center hubs in 2023, and matches Anhui's 65% target for the Wuhu cluster. Occupied capacity is assumed to be all AI chips.
44 MW for computing57 MW in all1 building runningLand clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after.
No power for computing yet
Power, chips, money and water.
Epoch AI's estimates as of Nov 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.
Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.
Owners, users and builders.
As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.
Not known
No wider project named
Not named
Not named
Not named
The chips, counted.
The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.
| Chip | Designer | How many | Since | How Epoch knows |
|---|---|---|---|---|
| Ascend 910C | Huawei | 22,759 est. | Nov 1, 2026 | Cumulative count. Epoch's AI Chip Sales data ends in Q2 2026, so H2 2026 volumes come from Epoch's Huawei roadmap report (https://epoch.ai/publications/huaweis-roadmap-to-2031): 750k Ascend 950PR over Q2–Q4 2026, 320k 950DT in Q4 2026, and the rest of the 430k 910Cs. Each new building's chip power mirrors the mix sold in the quarter that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip. |
| Ascend 950PR | Huawei | 33,085 est. | Nov 1, 2026 | Cumulative count. Epoch's AI Chip Sales data ends in Q2 2026, so H2 2026 volumes come from Epoch's Huawei roadmap report (https://epoch.ai/publications/huaweis-roadmap-to-2031): 750k Ascend 950PR over Q2–Q4 2026, 320k 950DT in Q4 2026, and the rest of the 430k 910Cs. Each new building's chip power mirrors the mix sold in the quarter that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip. |
| H20 | Nvidia | 83,555 est. | Nov 1, 2025 | Cumulative count. Each new building's chip power (TDP) mirrors the mix of H20, Ascend 910B and Ascend 910C chip power sold in the quarter of Epoch's AI Chip Sales data (https://epoch.ai/data/ai-chip-sales?view=graph&tab=h100_equivalents) that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip. Huawei Cloud's ModelArts documentation limits its H20 image to the CN North-Ulanqab1 and East China 2 (Wuhu) regions. |
| Ascend 910B | Huawei | 33,256 est. | Nov 1, 2025 | Cumulative count. Each new building's chip power (TDP) mirrors the mix of H20, Ascend 910B and Ascend 910C chip power sold in the quarter of Epoch's AI Chip Sales data (https://epoch.ai/data/ai-chip-sales?view=graph&tab=h100_equivalents) that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip. |
Wuhu, China
Address in Epoch AI's records: Wuhu, China.
Also in China
Where the facts come from.
The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.
- Huawei Wuhu in Epoch AI's directoryepoch.ai
- Epoch AI's calculations for this siteGoogle Sheets
Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/huawei-wuhu