Wednesday, November 25, 2026 · Edition updated 6:00 AM ETWED, NOV 25 editionNext edition in Next in --:--:--
Intelligence Progress
Running and growing · Wuhu, China

Huawei Wuhu

Huawei Wuhu is an AI data center in Wuhu, China, owned by Huawei. Epoch AI estimates it draws 197 MW for computing, rising to 453 MW by Dec 2027.

  • 197 MWfor computing now, #26 of the 96 Epoch AI tracks
  • 453 MWplanned by Dec 2027
  • $7.5 billionbuilt so far, Epoch AI's estimate in 2025 dollars
197 MW now
How it grew

Watched from above.

Epoch AI's dated notes on this site, from satellite images, permits and company statements, with the power it estimates at each step. Steps after today are its projection.

0 MW100 MW200 MW300 MW400 MW500 MW20232024202520262027Dec 1, 2022: 0 MWJan 1, 2025: 44 MWMar 1, 2025: 118 MWNov 1, 2025: 156 MWNov 1, 2026: 197 MWDec 31, 2026: 360 MW (projected)Dec 1, 2027: 453 MW (projected)0 MW100 MW200 MW300 MW400 MW500 MW20232024202520262027Dec 1, 2022: 0 MWJan 1, 2025: 44 MWMar 1, 2025: 118 MWNov 1, 2025: 156 MWNov 1, 2026: 197 MWDec 31, 2026: 360 MW (projected)Dec 1, 2027: 453 MW (projected)
  1. Epoch AI's projection

    All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is excluded due to insufficient cooling. The time from observed land-clearing to operational is 23-26 months based on previous buildings. As with the other buildings, we assume 65% rack occupancy.

    453 MW for computing (was 360 MW)589 MW in all8 buildings running
  2. Epoch AI's projection

    Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is about 3.7x more power than one of the previous buildings, based on the size and quantity of cooling and backup generator equipment observed in satellite imagery. As with the other buildings, we assume 65% rack occupancy.

    360 MW for computing (was 197 MW)468 MW in all6 buildings running
  3. Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

    197 MW for computing (was 156 MW)256 MW in all5 buildings running
  4. On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in approximately one month, given that it is structurally complete and 75% of its cooling looks to be installed. On the east campus, building 9 is under construction.

    156 MW for computing202 MW in all4 buildings running
  5. Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining.

    156 MW for computing202 MW in all4 buildings running
  6. Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have sufficient cooling for AI despite its backup generators. The remaining three buildings, one per campus, have not begun construction.

    156 MW for computing202 MW in all4 buildings running
  7. Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

    156 MW for computing (was 118 MW)202 MW in all4 buildings running
  8. Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but as of 2026 does not have the cooling sufficient for AI. Assumes a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

    118 MW for computing (was 44 MW)153 MW in all3 buildings running
  9. The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. We multiply each building's estimated capacity by an assumed 65% rack occupancy rate. This is close to the ~62–64% reported for Wuhu and other national data center hubs in 2023, and matches Anhui's 65% target for the Wuhu cluster. Occupied capacity is assumed to be all AI chips.

    44 MW for computing57 MW in all1 building running
  10. Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after.

    No power for computing yet
The numbers

Power, chips, money and water.

Epoch AI's estimates as of Nov 1, 2026. IT power is what the computers draw; the total adds cooling and the rest of the building.

197 MWIT power, for the computersNov 1, 2026
256 MWtotal power, cooling included
453 MWIT power planned by Dec 2027
53,000computing power, counted as Nvidia H100 chips
$7.5 billioncapital cost so far: $5.1 billion for chips and computers, $2.3 billion for the buildings, power and land
$17 billioncapital cost once finished, by Dec 2027
$0.2 billiona year to run (power, staff, upkeep, taxes, water)
No estimateof water use from Epoch AI for this site

Costs are Epoch AI's model, about $38 billion per gigawatt of IT power in 2025 dollars, not company figures. Running and growing drawing power now, and Epoch AI projects more to come.

Who's behind it

Owners, users and builders.

As Epoch AI records them. The owner is the company that owns the chips, which may not own the building. Who uses a site is often secret, so Epoch says how sure it is.

Owns the chips

Huawei

Uses it

Not known

Part of

No wider project named

Investors

Not named

Builders

Not named

Power from

Not named

What's inside

The chips, counted.

The AI chips at this site by Epoch AI's latest count. Most counts are estimates from the building's power; those marked disclosed come from the company.

ChipDesignerHow manySinceHow Epoch knows
Ascend 910CHuawei22,759 est.Nov 1, 2026Cumulative count. Epoch's AI Chip Sales data ends in Q2 2026, so H2 2026 volumes come from Epoch's Huawei roadmap report (https://epoch.ai/publications/huaweis-roadmap-to-2031): 750k Ascend 950PR over Q2–Q4 2026, 320k 950DT in Q4 2026, and the rest of the 430k 910Cs. Each new building's chip power mirrors the mix sold in the quarter that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip.
Ascend 950PRHuawei33,085 est.Nov 1, 2026Cumulative count. Epoch's AI Chip Sales data ends in Q2 2026, so H2 2026 volumes come from Epoch's Huawei roadmap report (https://epoch.ai/publications/huaweis-roadmap-to-2031): 750k Ascend 950PR over Q2–Q4 2026, 320k 950DT in Q4 2026, and the rest of the 430k 910Cs. Each new building's chip power mirrors the mix sold in the quarter that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip.
H20Nvidia83,555 est.Nov 1, 2025Cumulative count. Each new building's chip power (TDP) mirrors the mix of H20, Ascend 910B and Ascend 910C chip power sold in the quarter of Epoch's AI Chip Sales data (https://epoch.ai/data/ai-chip-sales?view=graph&tab=h100_equivalents) that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip. Huawei Cloud's ModelArts documentation limits its H20 image to the CN North-Ulanqab1 and East China 2 (Wuhu) regions.
Ascend 910BHuawei33,256 est.Nov 1, 2025Cumulative count. Each new building's chip power (TDP) mirrors the mix of H20, Ascend 910B and Ascend 910C chip power sold in the quarter of Epoch's AI Chip Sales data (https://epoch.ai/data/ai-chip-sales?view=graph&tab=h100_equivalents) that contains the date 4 months before it came online. Chips = that chip's share of IT power ÷ its all-in IT power per chip.
Sources

Where the facts come from.

The primary sources Epoch AI lists for this site: permits, filings, company posts and reporting. Epoch's own page and workings are last.

  1. Huawei Wuhu in Epoch AI's directoryepoch.ai
  2. Epoch AI's calculations for this siteGoogle Sheets

Data: Epoch AI, ‘AI data centers’, CC BY 4.0, read Nov 25, 2026. Page: Intelligence Progress, https://intelligenceprogress.com/data-centers/huawei-wuhu